1918 Lake St
San Francisco permit 202203291107 · Seacliff
1st fl: horizontal enlargement. add family room & bathroom. 2nd fl: replace existing deck. add stair well and stairs to the first floor. no bldg height increase. no change on front of the building.
- Filed
- Mar 29, 2022
- Issued
- Jun 10, 2024 (26 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 29, 2022 | Apr 7, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 7, 2022 | Oct 31, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 7, 2022 | Apr 15, 2024 | In Progress |
Planning neighborhood notice Planning · CP-NP | Aug 23, 2023 | Sep 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Nov 1, 2023 | Dec 5, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2023 | Nov 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2023 | Nov 6, 2023 | Approved-Stipulated |
Building pre-screening Building Inspection · PRE-BLDG | Nov 2, 2023 | Nov 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Mar 8, 2024 | Mar 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Mar 15, 2024 | Mar 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 15, 2024 | Mar 25, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2024 | Mar 18, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 22, 2024 | Mar 22, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 26, 2024 | Apr 2, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 3, 2024 | Apr 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 12, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2024 | Apr 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2024 | Jun 10, 2024 | Administrative |
Addendum 1: Final - structural, mechanical, title 24.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 17, 2024 | Jun 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jun 18, 2024 | Jun 18, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jun 24, 2024 | Jun 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 12, 2024 | Jul 12, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Aug 13, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Aug 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2024 | Jul 15, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 12, 2024 | Feb 25, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 21, 2024 | Dec 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Dec 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2024 | Nov 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 21, 2024 | Nov 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2025 | Feb 11, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 13, 2025 | Feb 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 13, 2025 | Feb 20, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2025 | Feb 24, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 13, 2025 | Feb 20, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 25, 2025 | Apr 4, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $335,643
| Name | Role | License on permit |
|---|---|---|
| Baek Young Ahn Baek Young Ahn, Aia | Architect | C19749 |
| Vitezslav Hanacek Vit Hanacek, Pe | Engineer | C-75786 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023