2119 29th Av
San Francisco permit 202203291152 · Sunset/Parkside
1- remodeling the existing dwelling and addition of 428 sq ft floor area as a new m. bedroom & m. bathroom at the garage level. 2- adding new junior adu (493 sq ft) to basement level (1 bedroom, 1 bathroom, living area, laundry and kitchen.
- Filed
- Mar 29, 2022
- Issued
- Nov 8, 2024 (31 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 65 stops across 6 departments
- Comments issued
- 19 times, by Permit Center, Planning, Building Inspection, Fire Department, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 29, 2022 | Apr 5, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 5, 2022 | Dec 6, 2022 | — |
Permit Processing Center Building Inspection · PPC | Apr 5, 2022 | Apr 18, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Aug 9, 2022 | Aug 25, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2022 | Apr 18, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 8, 2022 | Apr 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 8, 2022 | Dec 21, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 8, 2022 | Dec 12, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 4, 2023 | Apr 14, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 4, 2023 | Apr 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 4, 2023 | Apr 13, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 4, 2023 | Apr 6, 2023 | — |
Development fee collection Building Inspection · DFCU | Apr 18, 2023 | Apr 18, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2023 | Nov 8, 2024 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 14, 2024 | Nov 27, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Nov 14, 2024 | Dec 31, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 17, 2024 | Dec 30, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 27, 2024 | Jan 13, 2025 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Dec 31, 2024 | Jan 6, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jan 6, 2025 | Jan 9, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 6, 2025 | Jan 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 6, 2025 | Jan 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 6, 2025 | Jan 13, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 6, 2025 | Jan 9, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 6, 2025 | Feb 21, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 6, 2025 | Jan 10, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 6, 2025 | Oct 20, 2026 | Administrative |
Permit Center Permit Center · PERMIT-CTR | Jan 13, 2025 | Jan 13, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 1, 2025 | Oct 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Oct 1, 2025 | Oct 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 1, 2025 | Oct 7, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 1, 2025 | Oct 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 1, 2025 | Oct 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 1, 2025 | Oct 8, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 1, 2025 | Oct 8, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 24, 2026 | Mar 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 24, 2026 | Mar 6, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2026 | Feb 25, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 24, 2026 | Mar 5, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2026 | Feb 25, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 24, 2026 | Mar 19, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2026 | Mar 9, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Mar 3, 2026 | Mar 3, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2026 | Mar 4, 2026 | Approved |
Zoning review Planning · CP-ZOC | Jun 11, 2026 | Jun 25, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 11, 2026 | Jun 26, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 11, 2026 | Jun 18, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Jun 11, 2026 | Jun 16, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 11, 2026 | Jun 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 11, 2026 | Jun 22, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2026 | Jun 22, 2026 | Approved |
Zoning review Planning · CP-ZOC | Sep 2, 2026 | Oct 5, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 2, 2026 | Sep 11, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 2, 2026 | Sep 8, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 2, 2026 | Sep 4, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 2, 2026 | Sep 4, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 2, 2026 | Sep 17, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 2, 2026 | Sep 11, 2026 | Approved |
Building plan review Building Inspection · BLDG | Sep 29, 2026 | Oct 14, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 29, 2026 | Oct 2, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Sep 29, 2026 | Sep 30, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 29, 2026 | Oct 1, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 29, 2026 | Oct 15, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 29, 2026 | Oct 2, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2026 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Firas A Jandali Jedco Consulting Engineer | Engineer | 3031 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017