41 Girard St
San Francisco permit 202203311333 · Portola
Addition of second unit at lower level. replace deck at rear of upper floor with acces to yard.
- Filed
- Mar 31, 2022
- Issued
- Aug 16, 2022 (5 months after filing)
- Completed
- Dec 5, 2023 (16 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 12 stops across 4 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Mar 31, 2022 | Mar 31, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 31, 2022 | Mar 31, 2022 | — |
Intake Building Inspection · INTAKE | Apr 28, 2022 | Apr 28, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 28, 2022 | Apr 28, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 28, 2022 | Apr 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 28, 2022 | Apr 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 28, 2022 | Apr 28, 2022 | — |
Intake Building Inspection · INTAKE | Jun 17, 2022 | Jun 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 17, 2022 | Jun 17, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jun 21, 2022 | Jun 21, 2022 | — |
Development fee collection Building Inspection · DFCU | Aug 9, 2022 | Aug 9, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 16, 2022 | Aug 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $98,000
| Name | Role | License on permit |
|---|---|---|
| Albert C Law | Architect | C38812 |
| Zhuren Lawrence Liao | Engineer | 3273 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2023