220 Geary St
San Francisco permit 202204011386 · Financial District/South Beach
Union square/market st station concourse level - construct 2 vendor kiosks; convert 2 (e) storage to all gender accessible restroom; kiosks & all gender will include elec and plumb for new lightings, power and (n) water use fixtures; (e) undeveloped space to be renovated to a down-time room reserv
- Filed
- Apr 1, 2022
- Issued
- Sep 30, 2022 (6 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 1, 2022 | Apr 1, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 1, 2022 | Apr 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 1, 2022 | Apr 1, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 8, 2022 | Apr 8, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 8, 2022 | Apr 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 8, 2022 | Apr 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 8, 2022 | Apr 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 21, 2022 | Apr 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 27, 2022 | Jul 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 27, 2022 | Apr 27, 2022 | — |
Public Works disability access review Public Works · PW-DAC | May 18, 2022 | Jun 28, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 21, 2022 | Jun 21, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2022 | Jul 8, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2022 | Aug 1, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2022 | Aug 24, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 24, 2022 | Aug 24, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 2, 2022 | Sep 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 30, 2022 | Sep 30, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Issued
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Mei-Mei Chan Mei Architects | Architect | C-29350 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2018