CheckMyDesigner

644 Russia Av

San Francisco permit 202204051546 · Excelsior

ADUFull plan reviewIssued
Street view · Apr 2019
Google Street View of 644 Russia Av, Apr 2019
Scope of work
As written on the permit application.

Addition of one adu unit at the first floor under the state adu program.

Timeline
Key dates from the city record.
Filed
Apr 5, 2022
Issued
Aug 31, 2022 (5 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
6 times

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Planning review

Planning · CP-GEN

Apr 7, 2022—

Zoning review

Planning · CP-ZOC

Jul 28, 2022—

Building plan review

Building Inspection · BLDG

Jul 29, 2022—

Structural plan approval

Building Inspection · PAD-STR

Jul 29, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jul 8, 2022—

Fire prevention review

Fire Department · SFFD

Jul 13, 2022—

Street use and mapping

Public Works · DPW-BSM

Apr 12, 2022—

Urban forestry

Public Works · DPW-BUF

Aug 10, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 18, 2022—

Development fee collection

Building Inspection · DFCU

Aug 18, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 8, 2022—

Street use and mapping

Public Works · DPW-BSM

Jul 11, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jul 20, 2022—

Street use and mapping

Public Works · DPW-BSM

Jul 21, 2022—

Fire prevention review

Fire Department · SFFD

Jul 22, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 22, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 29, 2022—

Zoning review

Planning · CP-ZOC

Jul 28, 2022—

Building plan review

Building Inspection · BLDG

Aug 4, 2022—

Zoning review

Planning · CP-ZOC

Aug 11, 2022—

Street use and mapping

Public Works · DPW-BSM

Aug 11, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 11, 2022—

Urban forestry

Public Works · DPW-BUF

Aug 29, 2022—

Central Permit Bureau

Building Inspection · CPB

Aug 31, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$86,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Alex Chuan Kin LauEngineerC75773
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204051546 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record