644 Russia Av
San Francisco permit 202204051546 · Excelsior
Addition of one adu unit at the first floor under the state adu program.
- Filed
- Apr 5, 2022
- Issued
- Aug 31, 2022 (5 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Apr 5, 2022 | Apr 7, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 7, 2022 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2022 | Jul 29, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Apr 7, 2022 | Jul 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2022 | Jul 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 7, 2022 | Jul 13, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2022 | Apr 12, 2022 | — |
Urban forestry Public Works · DPW-BUF | Apr 7, 2022 | Aug 10, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2022 | Apr 18, 2022 | — |
Development fee collection Building Inspection · DFCU | Apr 7, 2022 | Aug 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 8, 2022 | Jul 8, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2022 | Jul 11, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2022 | Jul 20, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jul 19, 2022 | Jul 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2022 | Jul 22, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2022 | Jul 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 19, 2022 | Aug 29, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jul 28, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 4, 2022 | Aug 4, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 11, 2022 | Aug 11, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 11, 2022 | Aug 11, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 11, 2022 | Aug 11, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 19, 2022 | Aug 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 29, 2022 | Aug 31, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $86,000
| Name | Role | License on permit |
|---|---|---|
| Alex Chuan Kin Lau | Engineer | C75773 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019