428 15th Av
San Francisco permit 202204071831 · Outer Richmond
To erect 4 stories, no basment, type v-b, 2-units building.
- Filed
- Apr 7, 2022
- Issued
- May 15, 2024 (25 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 73 stops across 7 departments
- Comments issued
- 20 times, by Building Inspection, Fire Department, Public Utilities, Public Works, Permit Center, Planning
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Public health review Public Health · HEALTH | Jan 24, 2022 | Feb 24, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Apr 7, 2022 | Apr 7, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 15, 2022 | Feb 14, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 14, 2023 | Feb 14, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 15, 2023 | Nov 9, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 28, 2023 | Mar 2, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2023 | Apr 18, 2023 | — |
Fire prevention review Fire Department · SFFD | May 1, 2023 | Oct 19, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 17, 2023 | May 19, 2023 | — |
Urban forestry Public Works · DPW-BUF | May 19, 2023 | Jun 21, 2023 | — |
Urban forestry Public Works · DPW-BUF | Sep 20, 2023 | Sep 20, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 21, 2023 | Oct 3, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2023 | Oct 11, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 18, 2023 | Oct 19, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 30, 2023 | Nov 1, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 9, 2023 | Dec 4, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 15, 2023 | Nov 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 4, 2023 | Dec 14, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 18, 2023 | Dec 20, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Dec 20, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 21, 2023 | Dec 21, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 21, 2023 | May 15, 2024 | Administrative |
Addendum 1: Foundation & superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building pre-screening Building Inspection · PRE-BLDG | Apr 1, 2024 | Apr 1, 2025 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 14, 2024 | Nov 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 22, 2024 | Nov 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 25, 2024 | Dec 13, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 25, 2024 | Dec 5, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Nov 25, 2024 | Nov 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 25, 2024 | Nov 25, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Nov 25, 2024 | Jun 27, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 28, 2025 | Apr 1, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 23, 2025 | Jun 18, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2025 | Jun 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2025 | Sep 8, 2025 | Administrative |
Addendum 2: Architectural & mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2024 | Nov 22, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 12, 2024 | Dec 24, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Mar 31, 2025 | Apr 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2025 | Apr 15, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 15, 2025 | Jun 2, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 15, 2025 | May 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 15, 2025 | Apr 17, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2025 | Apr 16, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 15, 2025 | Apr 30, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 15, 2025 | Apr 15, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 15, 2025 | May 27, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Apr 15, 2025 | Aug 25, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | May 27, 2025 | May 27, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2025 | Jun 3, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2025 | Jul 10, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 18, 2025 | Jun 23, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 18, 2025 | Jun 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2025 | Jun 27, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jun 18, 2025 | Jul 14, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2025 | Jun 26, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 18, 2025 | Jun 25, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jul 9, 2025 | Jul 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 28, 2025 | Aug 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 28, 2025 | Jul 31, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jul 28, 2025 | Jul 28, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2025 | Jul 29, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 28, 2025 | Aug 19, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2025 | Jul 29, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 28, 2025 | Jul 30, 2025 | Approved |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 20, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Aug 8, 2025 | Aug 8, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 14, 2025 | Aug 18, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2025 | Aug 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2025 | Aug 15, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 19, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 14, 2025 | Aug 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 19, 2025 | Aug 19, 2025 | Administrative |
Urban forestry Public Works · DPW-BUF | Aug 19, 2025 | Aug 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 25, 2025 | Sep 8, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,879,780
| Name | Role | License on permit |
|---|---|---|
| Mark Jeffrey Topetcher Topetcher Architecture Inc. | Architect | C21678 |
| Zachary Joseph Maddry Dma Rc Studio | Architect | C-30718 |
| David W Kane Harrell Kane S.E. Inc. | Engineer | S-5278 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022