San Francisco permit 202204142225 · Sunset/Parkside

Deck, stairs or patio cover (type unconfirmed)Full plan reviewIssued
Street view · May 2022
Google Street View of 1718 Great Hy, May 2022
Scope of work
As written on the permit application.

Infill existing light well at north side of property, no shared windows with adjacent propoerty. add stairs and landings at rear of building as permitted obstrucitons per zab-05 & sfpc sec 136

Timeline
Key dates from the city record.
Filed
Apr 14, 2022
Issued
Sep 25, 2023 (17 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
Once, by Building Inspection
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 4, 2022—

Zoning review

Planning · CP-ZOC

Nov 23, 2022—

Permit Processing Center

Building Inspection · PPC

Sep 6, 2023—

Planning neighborhood notice

Planning · CP-NP

Aug 31, 2022—

Building plan review

Building Inspection · BLDG

Aug 16, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 12, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 11, 2023—

Street use and mapping

Public Works · DPW-BSM

Apr 17, 2023—

Building pre-screening

Building Inspection · PRE-BLDG

May 8, 2023—

Zoning review

Planning · CP-ZOC

Jul 7, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 9, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 19, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 12, 2023—

Zoning review

Planning · CP-ZOC

Jul 26, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 24, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 3, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 22, 2023Approved

Zoning review

Planning · CP-ZOC

Sep 6, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Aug 28, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 24, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Sep 25, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$167,350
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Michael Shad Howard Beazer

Studio 22 Design

ArchitectC-33524
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204142225 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record