Infill existing light well at north side of property, no shared windows with adjacent propoerty. add stairs and landings at rear of building as permitted obstrucitons per zab-05 & sfpc sec 136
- Filed
- Apr 14, 2022
- Issued
- Sep 25, 2023 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2022 | May 4, 2022 | — |
Zoning review Planning · CP-ZOC | May 4, 2022 | Nov 23, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 4, 2022 | Sep 6, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Aug 11, 2022 | Aug 31, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2023 | Aug 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2023 | Jul 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2023 | May 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2023 | Apr 17, 2023 | — |
Building pre-screening Building Inspection · PRE-BLDG | May 8, 2023 | May 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 5, 2023 | Jul 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 5, 2023 | Aug 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 5, 2023 | Jul 19, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 12, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 21, 2023 | Jul 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2023 | Jul 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Aug 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2023 | Aug 22, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 22, 2023 | Sep 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2023 | Aug 23, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2023 | Aug 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2023 | Aug 24, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 6, 2023 | Sep 25, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $167,350
| Name | Role | License on permit |
|---|---|---|
| Michael Shad Howard Beazer Studio 22 Design | Architect | C-33524 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022