1005 Powell St
San Francisco permit 202204142240 · Nob Hill
To comply with nov#201803424.replace entries.former residential lobby will become sro manager office.reconfigure entry.warp sidewalk to provide landing.add ramp in the office for accessibility.modify(e)storage areas to a trash room, lounge & restroom.mep improvements.infill vault&cover at sidewalk
- Filed
- Apr 14, 2022
- Issued
- Oct 13, 2022 (6 months after filing)
- Completed
- Mar 15, 2024 (17 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 23 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Apr 14, 2022 | Apr 14, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Apr 14, 2022 | Apr 14, 2022 | — |
Intake Building Inspection · INTAKE | Apr 14, 2022 | Apr 14, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 14, 2022 | Apr 14, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2022 | Apr 14, 2022 | — |
Building plan review Building Inspection · BLDG | Apr 14, 2022 | Apr 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2022 | Apr 14, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 14, 2022 | Apr 14, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2022 | Apr 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2022 | Apr 14, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Apr 15, 2022 | Oct 4, 2022 | — |
Intake Building Inspection · INTAKE | Apr 22, 2022 | Apr 22, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Apr 22, 2022 | Apr 22, 2022 | — |
Fire prevention review Fire Department · SFFD | Apr 22, 2022 | Apr 22, 2022 | — |
Intake Building Inspection · INTAKE | Sep 30, 2022 | Sep 30, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 30, 2022 | Sep 30, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 30, 2022 | Sep 30, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 3, 2022 | Oct 3, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 3, 2022 | Oct 3, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2022 | Oct 3, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 5, 2022 | Oct 5, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 5, 2022 | Oct 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 13, 2022 | Oct 13, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Perez Studio Perez | Architect | C28030 |
| David Owen Crestfield Triangle Engineering | Engineer | C050629 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026