Scope of work
As written on the permit application.

Project consists of new state accessory dwelling unit, including remodel of existing 1st floor kitchen, family room, bath and office, plus creation of two new bedrooms and new bathroom, in conjunction with remodeling of main house (under separate permit no.202204142257).see dwg. "permit note"

Timeline
Key dates from the city record.
Filed
Apr 14, 2022
Issued
Jan 26, 2024 (21 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
33 stops across 4 departments
Comments issued
Twice, by Building Inspection
Put on hold
9 times
Review stopFinishedResult

Mechanical and energy plan review

Building Inspection · MECH

Jul 13, 2023—

Central Permit Bureau

Building Inspection · CPB

Sep 22, 2022—

Permit Processing Center

Building Inspection · PPC

Jan 18, 2024Administrative

Zoning review

Planning · CP-ZOC

Dec 14, 2022—

Building plan review

Building Inspection · BLDG

Dec 24, 2022—

Building plan review

Building Inspection · BLDG

Jul 6, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 23, 2023—

Street use and mapping

Public Works · DPW-BSM

Jul 6, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 11, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 28, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 7, 2023—

Zoning review

Planning · CP-ZOC

Oct 17, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 13, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 10, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 27, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 8, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 19, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 5, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Nov 22, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Oct 17, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 23, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 14, 2023—

Building plan review

Building Inspection · BLDG

Nov 7, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 30, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 25, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 18, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jan 4, 2024Approved

Zoning review

Planning · CP-ZOC

Jan 9, 2024—

Building plan review

Building Inspection · BLDG

Jan 17, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 28, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 8, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 26, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$441,079
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Robert Allen Boles

Beausoleil Architecture

ArchitectC016978
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204142255 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record