725 Darien Wy
San Francisco permit 202204142257 · West of Twin Peaks
Project consists remodeling of main house including relocation of interior stair, remodeling of garage & laundry, new hydronic heating system for entire house, remodeling of (e) bathroom & closets on 2/f, repair 'in kind' of (e) exterior front stairs & (e) front window at 2/f & new paving & planting
- Filed
- Apr 14, 2022
- Issued
- Jan 26, 2024 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 34 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 14, 2022 | Sep 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 22, 2022 | Jan 18, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Sep 23, 2022 | Dec 14, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 15, 2022 | Dec 23, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 15, 2022 | Jul 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2022 | May 23, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2022 | Jul 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2022 | Jan 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2023 | Jun 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 28, 2023 | Jul 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2023 | Oct 17, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 7, 2023 | Jul 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2023 | Jul 10, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2023 | Jul 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 1, 2023 | Sep 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 1, 2023 | Sep 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2023 | Sep 5, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 1, 2023 | Sep 8, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 13, 2023 | Nov 22, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 17, 2023 | Oct 17, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 23, 2023 | Oct 23, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 23, 2023 | Nov 14, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 23, 2023 | Nov 7, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2023 | Oct 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 23, 2023 | Oct 25, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 20, 2023 | Dec 20, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 26, 2023 | Jan 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 26, 2023 | Jan 9, 2024 | — |
Building plan review Building Inspection · BLDG | Dec 26, 2023 | Jan 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 26, 2023 | Dec 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 26, 2023 | Jan 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2023 | Jan 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 18, 2024 | Jan 26, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $106,815
| Name | Role | License on permit |
|---|---|---|
| Robert Allen Boles Beausoleil Architecture | Architect | C016978 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025