CheckMyDesigner

1274 Sanchez St

San Francisco permit 202204152312 · Noe Valley

AdditionFull plan reviewComplete
Street view · Feb 2022
Google Street View of 1274 Sanchez St, Feb 2022
Scope of work
As written on the permit application.

Interior alteration of the basement and first floor. partial horizontal addition at the north side yard. vertical addition of a (n) second floor above the (e) first floor. exterior facade alterations. (n) roof deck

Timeline
Key dates from the city record.
Filed
Apr 15, 2022
Issued
Jun 27, 2023 (14 months after filing)
Completed
Nov 18, 2025 (29 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
22 stops across 4 departments
Comments issued
4 times, by Building Inspection, Public Utilities
Put on hold
3 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Apr 15, 2022—

Zoning review

Planning · CP-ZOC

Feb 14, 2023—

Planning neighborhood notice

Planning · CP-NP

Jan 19, 2023—

Building plan review

Building Inspection · BLDG

May 4, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 1, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 5, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 8, 2023—

Zoning review

Planning · CP-ZOC

Jun 14, 2023—

Permit Processing Center

Building Inspection · PPC

Jun 20, 2023—

Central Permit Bureau

Building Inspection · CPB

Jun 27, 2023—

Addendum 1: Arch / structural / t-24 / final.

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jun 27, 2023—

Building plan review

Building Inspection · BLDG

Aug 8, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 14, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 20, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Sep 21, 2023Approved

Building plan review

Building Inspection · BLDG

Oct 2, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 4, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Oct 6, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Oct 13, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Oct 19, 2023Approved

Permit Processing Center

Building Inspection · PPC

Oct 20, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Oct 26, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Renato M Jose

Renato Jose I Architect

ArchitectC28111
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204152312 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record