1274 Sanchez St
San Francisco permit 202204152312 · Noe Valley
Interior alteration of the basement and first floor. partial horizontal addition at the north side yard. vertical addition of a (n) second floor above the (e) first floor. exterior facade alterations. (n) roof deck
- Filed
- Apr 15, 2022
- Issued
- Jun 27, 2023 (14 months after filing)
- Completed
- Nov 18, 2025 (29 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Public Utilities
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 15, 2022 | Apr 15, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 15, 2022 | Feb 14, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Dec 6, 2022 | Jan 19, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 15, 2023 | May 4, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 5, 2023 | Jun 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2023 | Jun 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 6, 2023 | Jun 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2023 | Jun 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 20, 2023 | Jun 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2023 | Jun 27, 2023 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 27, 2023 | Jun 27, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 27, 2023 | Aug 8, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 9, 2023 | Sep 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 20, 2023 | Sep 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2023 | Sep 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 2, 2023 | Oct 2, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Oct 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 4, 2023 | Oct 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 10, 2023 | Oct 13, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2023 | Oct 19, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 20, 2023 | Oct 20, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 20, 2023 | Oct 26, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Renato M Jose Renato Jose I Architect | Architect | C28111 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022