1304 Valencia St
San Francisco permit 202204202645 · Mission
Remodel existing ground level and second level. add a rear addition. demolish existing attic level storage and attic. create a new residential unit atop the existing second level.
- Filed
- Apr 20, 2022
- Issued
- Jan 23, 2024 (21 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 48 stops across 6 departments
- Comments issued
- 12 times, by Permit Center, Building Inspection, Fire Department, Public Works
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 20, 2022 | May 12, 2022 | — |
Building inspector Building Inspection · BID-INSP | Apr 22, 2022 | Apr 22, 2022 | — |
Code enforcement Building Inspection · CES | Apr 26, 2022 | Apr 26, 2022 | — |
Zoning review Planning · CP-ZOC | May 12, 2022 | Feb 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 12, 2022 | Aug 14, 2023 | In Progress |
Planning neighborhood notice Planning · CP-NP | Sep 28, 2022 | Oct 4, 2022 | — |
Planning discretionary review Planning · CP-DR | Nov 14, 2022 | Feb 22, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2023 | Jun 29, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 24, 2023 | Apr 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2023 | Mar 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2023 | Jul 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 17, 2023 | May 4, 2023 | — |
Fire prevention review Fire Department · SFFD | May 4, 2023 | Jun 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2023 | Jun 12, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 30, 2023 | Jul 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 30, 2023 | Aug 8, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jul 13, 2023 | Jul 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Aug 9, 2023 | Aug 14, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 9, 2023 | Aug 9, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 14, 2023 | Jan 23, 2024 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 28, 2024 | Mar 6, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Feb 29, 2024 | Feb 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 29, 2024 | Apr 16, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 1, 2024 | Mar 1, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 4, 2024 | Mar 4, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 10, 2024 | Apr 16, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 11, 2024 | Apr 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 16, 2024 | May 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2024 | May 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 16, 2024 | Apr 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2024 | Apr 18, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 16, 2024 | Jan 7, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | May 17, 2024 | May 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 8, 2024 | Jul 17, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 9, 2024 | Jul 9, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 6, 2024 | Aug 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 29, 2024 | Sep 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2024 | Sep 20, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 3, 2024 | Oct 11, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2024 | Nov 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 15, 2024 | Nov 15, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2024 | Dec 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2024 | Dec 16, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 4, 2024 | Dec 4, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2024 | Dec 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 17, 2024 | Dec 17, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jan 7, 2025 | Mar 6, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,712,178
| Name | Role | License on permit |
|---|---|---|
| Andrew Bruce Morrall Andrew Morrall Architect | Architect | C26696 |
| Lisa Wai Sum Tse Integrand Structural Engineer | Engineer | 4839 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026