2112 18th St
San Francisco permit 202204202652 · Potrero Hill
Re-build existing rear main level deck. add a roof deck with spiral staircases in the rear yard.
- Filed
- Apr 20, 2022
- Issued
- Jan 9, 2024 (21 months after filing)
- Completed
- Feb 6, 2026 (25 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 19 stops across 3 departments
- Comments issued
- 3 times, by Building Inspection
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 20, 2022 | Apr 21, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 21, 2022 | Jun 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 21, 2022 | Jul 24, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Oct 19, 2022 | Jun 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 6, 2023 | Jun 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 7, 2023 | Jul 20, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 21, 2023 | Jul 24, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 24, 2023 | Jan 9, 2024 | Administrative |
Addendum 1: Foundation, framing, decking, guardrails, siding, architectural
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 29, 2024 | Mar 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 4, 2024 | Mar 4, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 5, 2024 | Mar 5, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Mar 8, 2024 | Mar 8, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Mar 11, 2024 | Mar 11, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2024 | Mar 15, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 15, 2024 | May 17, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 15, 2024 | Aug 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 9, 2024 | Jul 22, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 7, 2024 | Aug 20, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2024 | Apr 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $56,736
| Name | Role | License on permit |
|---|---|---|
| Andrew Bruce Morrall Andrew Morrall Architect | Architect | C26696 |
| Adam Frederick Klein Bkg Structural Engineers | Engineer | S5941 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023