Scope of work
As written on the permit application.

T.i. for a take out only coffee shop in (e) shell. new non-structural partitions, storefront, equipment, fixtures, finishes, and mep upgrades.

Timeline
Key dates from the city record.
Filed
Apr 26, 2022
Issued
Jan 10, 2023 (9 months after filing)
Completed
Apr 13, 2023 (3 months after issuance)

For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
20 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
Twice

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Apartment and hotel inspection

Building Inspection · HIS

Apr 26, 2022—

Intake

Building Inspection · INTAKE

Apr 26, 2022—

Zoning review

Planning · CP-ZOC

May 5, 2022—

Mechanical and energy plan review

Building Inspection · MECH

May 6, 2022—

Fire prevention review

Fire Department · SFFD

May 6, 2022—

Public health review

Public Health · HEALTH

Sep 21, 2022—

Zoning review

Planning · CP-ZOC

Oct 24, 2022—

Building plan review

Building Inspection · BLDG

Oct 24, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Oct 24, 2022—

Electrical plan review

Building Inspection · MECH-E

Oct 24, 2022—

Fire prevention review

Fire Department · SFFD

Oct 24, 2022—

Street use and mapping

Public Works · DPW-BSM

Nov 21, 2022—

Public health review

Public Health · HEALTH

Nov 4, 2022—

Intake

Building Inspection · INTAKE

Nov 21, 2022—

Zoning review

Planning · CP-ZOC

Nov 21, 2022—

Building plan review

Building Inspection · BLDG

Nov 21, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Nov 21, 2022—

Fire prevention review

Fire Department · SFFD

Nov 21, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Dec 21, 2022—

Central Permit Bureau

Building Inspection · CPB

Jan 10, 2023—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Complete
Estimated cost
$220,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Niccolo Valerio

Valerio Architects

ArchitectC24228
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204263011 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record