1879 45th Av
San Francisco permit 202204283202 · Sunset/Parkside
Expanding rear of home to create an internal staircase to connect to new conditioned space in existing ground fl leve. renovating(e)ground fl to have new bath,bedroom & space,lower slab 7"(excavating 17.7cubic yards)no work to interior of level 2,no interior wall demo on level 1.
- Filed
- Apr 28, 2022
- Issued
- Aug 17, 2023 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 4, 2022 | May 20, 2022 | — |
Zoning review Planning · CP-ZOC | May 20, 2022 | Feb 17, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 20, 2022 | Aug 1, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Nov 20, 2022 | Dec 13, 2022 | — |
Building plan review Building Inspection · BLDG | Feb 24, 2023 | May 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2023 | Mar 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2023 | Mar 30, 2023 | — |
Building plan review Building Inspection · BLDG | May 1, 2023 | May 15, 2023 | — |
Zoning review Planning · CP-ZOC | May 15, 2023 | May 15, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | Jul 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2023 | May 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2023 | Aug 17, 2023 | Administrative |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 23, 2023 | Aug 25, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 25, 2023 | Sep 18, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 25, 2023 | Oct 2, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 25, 2023 | Sep 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 25, 2023 | Sep 5, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 25, 2023 | Mar 22, 2024 | — |
Building plan review Building Inspection · BLDG | Oct 6, 2023 | Oct 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 14, 2023 | Jan 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 5, 2024 | Feb 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 12, 2024 | Feb 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Feb 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 22, 2024 | Mar 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Mar 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Feb 26, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 29, 2024 | Feb 29, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2024 | Mar 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 21, 2024 | Mar 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 22, 2024 | Apr 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $213,358
| Name | Role | License on permit |
|---|---|---|
| David Townsend Brown | Engineer | C74826 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022