1879 45th Av

San Francisco permit 202204283202 · Sunset/Parkside

AdditionFull plan reviewCancelled
Street view · Mar 2022
Google Street View of 1879 45th Av, Mar 2022
Scope of work
As written on the permit application.

Expanding rear of home to create an internal staircase to connect to new conditioned space in existing ground fl leve. renovating(e)ground fl to have new bath,bedroom & space,lower slab 7"(excavating 17.7cubic yards)no work to interior of level 2,no interior wall demo on level 1.

Timeline
Key dates from the city record.
Filed
Apr 28, 2022
Issued
Aug 17, 2023 (16 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 5 departments
Comments issued
5 times, by Building Inspection, Fire Department
Put on hold
Twice

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 20, 2022—

Zoning review

Planning · CP-ZOC

Feb 17, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 1, 2023Administrative

Planning neighborhood notice

Planning · CP-NP

Dec 13, 2022—

Building plan review

Building Inspection · BLDG

May 1, 2023—

Street use and mapping

Public Works · DPW-BSM

Mar 1, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Mar 30, 2023—

Building plan review

Building Inspection · BLDG

May 15, 2023—

Zoning review

Planning · CP-ZOC

May 15, 2023—

Street use and mapping

Public Works · DPW-BSM

Jul 26, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 17, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 17, 2023Administrative

Addendum 1: Arch mep structural final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 25, 2023Administrative

Building plan review

Building Inspection · BLDG

Sep 18, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Oct 2, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 6, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 5, 2023Approved

Permit Processing Center

Building Inspection · PPC

Mar 22, 2024—

Building plan review

Building Inspection · BLDG

Oct 6, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Jan 12, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 5, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 12, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 23, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Mar 8, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 26, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 29, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 11, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 22, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 3, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Cancelled
Estimated cost
$213,358
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Townsend BrownEngineerC74826
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202204283202 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record