4128 24th St
San Francisco permit 202204283258 · Noe Valley
4-story rear addition (n) garage. 1st fl addition: family room; 2nd fl addition: kitchen reconfiguration, (n) bedroom & bath; 3rd fl addition: reconfigure attic & (n) office & (n) roof deck. (n) windows throughout.
- Filed
- Apr 28, 2022
- Issued
- Oct 30, 2023 (18 months after filing)
- Completed
- Feb 10, 2026 (27 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- 6 times, by Building Inspection, Public Works, Public Utilities
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 3, 2022 | May 3, 2022 | — |
Zoning review Planning · CP-ZOC | May 3, 2022 | Oct 5, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jul 18, 2022 | Jul 25, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 6, 2022 | Nov 22, 2022 | — |
Zoning review Planning · CP-ZOC | Mar 16, 2023 | Mar 16, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 10, 2023 | Aug 1, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 27, 2023 | Aug 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 1, 2023 | Aug 1, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 10, 2023 | Aug 17, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2023 | Sep 1, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 21, 2023 | Aug 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 1, 2023 | Sep 1, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2023 | Oct 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2023 | Oct 12, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 12, 2023 | Oct 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 19, 2023 | Oct 23, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Oct 23, 2023 | Oct 30, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $842,000
| Name | Role | License on permit |
|---|---|---|
| Michael P Ford Es Lo Design Studio | Architect | 36260 |
| Erevan O'neill One Design | Engineer | C75459 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022