450 Rhode Island St #1
San Francisco permit 202204293305 · Potrero Hill
Interior remodel; equipment update and minor demolition create order pick up area(not visible from the street)
- Filed
- Apr 29, 2022
- Issued
- Oct 31, 2022 (6 months after filing)
- Completed
- Dec 12, 2022 (1 month after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 10 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 29, 2022 | May 2, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | May 2, 2022 | May 2, 2022 | — |
Zoning review Planning · CP-ZOC | May 2, 2022 | Jul 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 2, 2022 | Oct 21, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2022 | Sep 27, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2022 | Aug 31, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 19, 2022 | Jul 26, 2022 | — |
Public health review Public Health · HEALTH | Jul 19, 2022 | Oct 19, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 31, 2022 | Sep 1, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 21, 2022 | Oct 31, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $32,872
| Name | Role | License on permit |
|---|---|---|
| Mariah B Meyer Brr | Architect | C37440 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026