27 A Brazil Av
San Francisco permit 202204293316 · Excelsior
Per legalization ord# 43-14, convert un-permitted in-law unit into a legal 2nd unit. install egress windows, smoke/carbon monoxide alarms. install landscaping per planning requirements, landscaping, permeable surface new street tree, and 2 bicycle parking spaces.
- Filed
- Dec 3, 2024
- Issued
- Jan 29, 2026 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 24 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Apr 29, 2022 | Apr 29, 2022 | — |
Zoning review Planning · CP-ZOC | Apr 29, 2022 | Aug 11, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 11, 2023 | Aug 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 14, 2023 | Aug 14, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Aug 14, 2023 | Aug 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 18, 2023 | Aug 18, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 18, 2023 | Aug 18, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2024 | Nov 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2024 | Dec 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 12, 2024 | Jan 9, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2024 | Dec 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 12, 2024 | Jan 13, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2024 | Dec 17, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 12, 2024 | Jan 23, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 12, 2024 | Dec 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2024 | Dec 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 12, 2024 | Jun 23, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Feb 24, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Mar 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 25, 2025 | Feb 25, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Apr 2, 2025 | Apr 2, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 28, 2025 | Apr 30, 2025 | Approved |
Development fee collection Building Inspection · DFCU | May 1, 2025 | May 16, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 23, 2025 | Jan 29, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $229,850
| Name | Role | License on permit |
|---|---|---|
| Samuel Kwong Arcus Architecture & Planning | Architect | C14679 |
| Alan Kiyoshi Toma Design Studio | Architect | C20518 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025