255 Capistrano Av
San Francisco permit 202205023368 · Outer Mission
New addition of bathroom, hallway, and bedroom at garage level. removal of rear patio roof.
- Filed
- May 2, 2022
- Issued
- Dec 10, 2024 (31 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 2, 2022 | May 12, 2023 | — |
Zoning review Planning · CP-ZOC | May 15, 2023 | Nov 30, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | May 15, 2023 | Dec 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 5, 2023 | Feb 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2023 | Dec 28, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2023 | Dec 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 5, 2023 | Dec 12, 2023 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 6, 2023 | Dec 6, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 13, 2024 | Aug 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2024 | Aug 19, 2024 | Approved |
Zoning review Planning · CP-ZOC | Aug 13, 2024 | Aug 13, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 13, 2024 | Aug 13, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 13, 2024 | Aug 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 25, 2024 | Oct 8, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 25, 2024 | Oct 28, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 25, 2024 | Oct 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Sep 30, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 25, 2024 | Sep 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 30, 2024 | Nov 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Oct 30, 2024 | Nov 7, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2024 | Nov 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 30, 2024 | Nov 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 30, 2024 | Dec 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 6, 2024 | Nov 13, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2024 | Dec 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $100,000
| Name | Role | License on permit |
|---|---|---|
| Devendra Singh Deshwal | Engineer | C89732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026