450 Harrison St
San Francisco permit 202205033463 · Financial District/South Beach
Install 1 standby tenant load diesel generator w/ (200 gal total) base fuel tank (e) concrete pad & 200 a ats/camlock near (e) at&t equipment area. integrate (n) generator with (e) service. install pull string w/ conduit 1 (n) 2" & 1 (n) 1" conduit/conductors install from (n) gen to (n) ats. 2 (n)..
- Filed
- May 3, 2022
- Issued
- Nov 17, 2022 (7 months after filing)
- Completed
- Not completed yet
- Review stops
- 16 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 3, 2022 | May 3, 2022 | — |
Zoning review Planning · CP-ZOC | May 3, 2022 | May 3, 2022 | — |
Building plan review Building Inspection · BLDG | May 3, 2022 | May 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 3, 2022 | May 3, 2022 | — |
Electrical plan review Building Inspection · MECH-E | May 3, 2022 | May 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | May 4, 2022 | Jun 13, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 14, 2022 | Aug 17, 2022 | — |
Public health review Public Health · HEALTH | Aug 2, 2022 | Aug 11, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 17, 2022 | Aug 24, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 25, 2022 | Nov 3, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 30, 2022 | Oct 6, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 6, 2022 | Oct 7, 2022 | — |
Public health review Public Health · HEALTH | Oct 14, 2022 | Oct 14, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 14, 2022 | Oct 17, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 3, 2022 | Nov 3, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 3, 2022 | Nov 17, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $25,000
| Name | Role | License on permit |
|---|---|---|
| Donald William George Geo Structural | Engineer | C62222 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026