As written on the permit application.

(n) window, (n) addition at 1st fl, (n) laundry, (n) kitchen, remodel (e) bathroom, 3rd fl rear & vertical adition, (n) roof deck, (n) siding.

Timeline
Key dates from the city record.
Filed
May 6, 2022
Issued
Dec 6, 2023 (19 months after filing)
Completed
Aug 21, 2025 (20 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 5 departments
Comments issued
None
Put on hold
4 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 10, 2022—

Zoning review

Planning · CP-ZOC

Mar 3, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 7, 2023—

Building plan review

Building Inspection · BLDG

Jun 13, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Apr 25, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 11, 2023—

Fire prevention review

Fire Department · SFFD

May 9, 2023—

Street use and mapping

Public Works · DPW-BSM

Mar 9, 2023—

Urban forestry

Public Works · DPW-BUF

Jun 27, 2023—

Zoning review

Planning · CP-ZOC

Apr 26, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 26, 2023—

Street use and mapping

Public Works · DPW-BSM

Apr 24, 2023—

Fire prevention review

Fire Department · SFFD

Jun 21, 2023—

Zoning review

Planning · CP-ZOC

May 26, 2023—

Mechanical and energy plan review

Building Inspection · MECH

May 24, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 21, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 31, 2023—

Zoning review

Planning · CP-ZOC

Jun 26, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 13, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 15, 2023—

Fire prevention review

Fire Department · SFFD

Jun 21, 2023—

Zoning review

Planning · CP-ZOC

Jul 17, 2023—

Building plan review

Building Inspection · BLDG

Jul 18, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 18, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 13, 2023—

Fire prevention review

Fire Department · SFFD

Jul 28, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 31, 2023Approved

Urban forestry

Public Works · DPW-BUF

Jul 31, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 20, 2023—

Central Permit Bureau

Building Inspection · CPB

Dec 6, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$744,900
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Jay Sherlock

Studio J. Architecture

ArchitectC33354
Franz Mutis

Design Everest Consulting Eng

EngineerC71963
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202205063720 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record