538 22nd Av
San Francisco permit 202205063720 · Outer Richmond
(n) window, (n) addition at 1st fl, (n) laundry, (n) kitchen, remodel (e) bathroom, 3rd fl rear & vertical adition, (n) roof deck, (n) siding.
- Filed
- May 6, 2022
- Issued
- Dec 6, 2023 (19 months after filing)
- Completed
- Aug 21, 2025 (20 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 6, 2022 | May 10, 2022 | — |
Zoning review Planning · CP-ZOC | May 10, 2022 | Mar 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 10, 2022 | Aug 7, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 6, 2023 | Jun 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 6, 2023 | Apr 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2023 | Apr 11, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 6, 2023 | May 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2023 | Mar 9, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 8, 2023 | Jun 27, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 24, 2023 | Apr 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 24, 2023 | Apr 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 24, 2023 | Apr 24, 2023 | — |
Fire prevention review Fire Department · SFFD | May 9, 2023 | Jun 21, 2023 | — |
Zoning review Planning · CP-ZOC | May 23, 2023 | May 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2023 | May 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 23, 2023 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2023 | May 31, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 12, 2023 | Jun 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2023 | Jun 13, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2023 | Jun 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 21, 2023 | Jun 21, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2023 | Jul 17, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 7, 2023 | Jul 18, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 7, 2023 | Jul 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2023 | Jul 13, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 7, 2023 | Jul 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2023 | Jul 31, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 7, 2023 | Jul 31, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 17, 2023 | Jul 20, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 7, 2023 | Dec 6, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $744,900
| Name | Role | License on permit |
|---|---|---|
| Jay Sherlock Studio J. Architecture | Architect | C33354 |
| Franz Mutis Design Everest Consulting Eng | Engineer | C71963 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2019