110 06th St

San Francisco permit 202205093804 · South of Market

Legalize or fix a violationOver-the-counter, with plansComplete
Street view · Sep 2026
Google Street View of 110 06th St, Sep 2026
Scope of work
As written on the permit application.

To comply with nov#202179781. proposed to open a grocery store:fruits, vegtable, packaged food, house hold items. propose to change floor tiles, add fridge, shelves, and storage. change of use from beauty supply to grocery store.

Timeline
Key dates from the city record.
Filed
May 9, 2022
Issued
Aug 18, 2022 (3 months after filing)
Completed
Feb 6, 2023 (6 months after issuance)

For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
17 stops across 5 departments
Comments issued
Not recorded for this permit
Put on hold
Once

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Building inspector

Building Inspection · BID-INSP

May 9, 2022—

Code enforcement

Building Inspection · CES

May 9, 2022—

Apartment and hotel inspection

Building Inspection · HIS

May 9, 2022—

Intake

Building Inspection · INTAKE

May 9, 2022—

Zoning review

Planning · CP-ZOC

May 11, 2022—

Building plan review

Building Inspection · BLDG

May 11, 2022—

Fire prevention review

Fire Department · SFFD

May 11, 2022—

Intake

Building Inspection · INTAKE

Jun 29, 2022—

Building plan review

Building Inspection · BLDG

Jun 29, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Jun 29, 2022—

Zoning review

Planning · CP-ZOC

Jul 1, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 1, 2022—

Public health review

Public Health · HEALTH

Aug 1, 2022—

Electrical plan review

Building Inspection · MECH-E

Aug 1, 2022—

Fire prevention review

Fire Department · SFFD

Aug 1, 2022—

Electrical plan review

Building Inspection · MECH-E

Aug 9, 2022—

Central Permit Bureau

Building Inspection · CPB

Aug 18, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
OTC alterations permit
Status
Complete
Estimated cost
$50,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mohammad Usman SadiqEngineerC67047
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202205093804 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record