1505 Dolores St
San Francisco permit 202205124169 · Noe Valley
Horizontal addition at rear of (e) house including kitech remodel, added work room, bathroom & home office. (n) rear deck & stairs. (n) roof deck.
- Filed
- May 12, 2022
- Issued
- Aug 28, 2024 (28 months after filing)
- Completed
- Jun 2, 2026 (21 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 3 times, by Permit Center, Building Inspection
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 12, 2022 | May 18, 2022 | — |
Zoning review Planning · CP-ZOC | May 18, 2022 | May 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 17, 2024 | Jun 3, 2024 | Approved-Stipulated |
Building pre-screening Building Inspection · PRE-BLDG | May 23, 2024 | May 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 5, 2024 | Jun 10, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 11, 2024 | Jun 24, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 26, 2024 | Jul 26, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 26, 2024 | Aug 28, 2024 | Administrative |
Addendum 1: Final- arch, t-24, foundation, superstrure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 25, 2025 | Feb 5, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Feb 8, 2025 | Feb 21, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 24, 2025 | Feb 24, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 24, 2025 | Mar 19, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 24, 2025 | Apr 5, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 24, 2025 | Feb 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 24, 2025 | Feb 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 24, 2025 | Feb 27, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 24, 2025 | Apr 2, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 24, 2025 | Jun 23, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 18, 2025 | Apr 18, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 9, 2025 | May 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2025 | Jun 2, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 2, 2025 | Jun 16, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jun 2, 2025 | Jun 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 2, 2025 | Jun 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 23, 2025 | Sep 9, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $225,000
| Name | Role | License on permit |
|---|---|---|
| Killian O'sullivan O'sullivan Architecture | Architect | C-30355 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022