424 Texas St
San Francisco permit 202205134264 · Potrero Hill
Erect a 4-story with zero basement, type vb, single family home.
- Filed
- May 13, 2022
- Issued
- Jul 15, 2024 (26 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 28 stops across 5 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 13, 2022 | May 23, 2022 | — |
Zoning review Planning · CP-ZOC | May 23, 2022 | Dec 22, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 23, 2022 | Jun 7, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 29, 2022 | Oct 6, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2022 | Aug 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 29, 2022 | Sep 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 29, 2022 | Jan 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 29, 2022 | Nov 1, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Aug 17, 2023 | Oct 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2023 | Aug 23, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2023 | Aug 25, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2023 | Aug 30, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2023 | Oct 4, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2023 | Oct 5, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2023 | Nov 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | May 7, 2024 | May 7, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 8, 2024 | May 9, 2024 | Approved |
Development fee collection Building Inspection · DFCU | May 9, 2024 | May 13, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 16, 2024 | May 30, 2024 | Approved |
Building plan review Building Inspection · BLDG | May 16, 2024 | May 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2024 | Jun 3, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 16, 2024 | Jun 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 16, 2024 | May 20, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2024 | May 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | May 30, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 4, 2024 | Jun 5, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2024 | Jun 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 7, 2024 | Jul 15, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $1,012,193
| Name | Role | License on permit |
|---|---|---|
| Beverly Ann Choe Bach Architecture | Payor | C29098 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022