225 Moncada Wy
San Francisco permit 202205234767 · West of Twin Peaks
Basement remodel and addition. (n) bathroom, electrical, foundation, structural, deck at 1st floor, rebuild 1st floor laundry room.
- Filed
- May 23, 2022
- Issued
- Apr 7, 2023 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 27, 2022 | May 27, 2022 | — |
Zoning review Planning · CP-ZOC | May 27, 2022 | Sep 20, 2022 | — |
Planning neighborhood notice Planning · CP-NP | Jul 18, 2022 | Jul 27, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 21, 2022 | Dec 16, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 16, 2022 | Dec 19, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2022 | Jan 6, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 9, 2023 | Jan 10, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 9, 2023 | Jan 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 10, 2023 | Apr 7, 2023 | — |
Addendum 1: Final - structural, mechanical, t-24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 10, 2023 | Oct 11, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 11, 2023 | Nov 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 17, 2023 | Jan 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 10, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 10, 2024 | Apr 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 13, 2024 | Feb 13, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | Feb 23, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2024 | Feb 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Apr 2, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2024 | Apr 3, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2024 | Apr 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 13, 2024 | May 13, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 14, 2024 | May 24, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 24, 2024 | Jun 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Lisa Ann Harvey Harvey Architecture | Architect | C23004 |
| Donald David Double D Engineering | Engineer | S3928 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2017