3756 Jackson St
San Francisco permit 202205254937 · Presidio Heights
Renovation of sfr. sow includes lower ground fl to create compliant ceiling height & upgrade fl layout. kitchen & bath remodel on all fl. lower 3rd fl ceiling height. exterior window & roof waterproofing / finishes. gh# 863-450-5651. ** maher: yes **
- Filed
- May 25, 2022
- Issued
- Apr 4, 2024 (22 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 6 departments
- Comments issued
- 5 times, by Building Inspection, Fire Department, Public Utilities
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 7, 2022 | Jun 7, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 7, 2022 | Feb 27, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 7, 2022 | Mar 27, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 27, 2023 | Dec 11, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 27, 2023 | Apr 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 27, 2023 | Mar 20, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 27, 2023 | Mar 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 27, 2023 | Mar 30, 2023 | Issued Comments |
Public health review Public Health · HEALTH | Feb 27, 2023 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 27, 2023 | Dec 14, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Dec 6, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 29, 2023 | Nov 29, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Nov 30, 2023 | Nov 30, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2023 | Dec 15, 2023 | Approved-Stipulated |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Feb 28, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Feb 22, 2024 | Feb 22, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Feb 23, 2024 | Feb 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 26, 2024 | Feb 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 28, 2024 | Feb 28, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 28, 2024 | Mar 7, 2024 | Approved |
Public health review Public Health · HEALTH | Feb 28, 2024 | Mar 14, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 20, 2024 | Mar 20, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 21, 2024 | Mar 21, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Mar 25, 2024 | Mar 26, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 27, 2024 | Apr 4, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,200,000
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clark Mcgriff Mcgriff Architects | Architect | C34047 |
| Jason R Powers Zfa Structural Engineers | Engineer | 76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2013