4340 25th St
San Francisco permit 202205255003 · Noe Valley
Interior remodel at ground floor - addition of new kitchen, new bathroom and storage area at ground floor. **building envelope will not be englarged. no new unit added.
- Filed
- May 25, 2022
- Issued
- Apr 9, 2024 (23 months after filing)
- Completed
- Oct 15, 2024 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 18 stops across 5 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 25, 2022 | May 31, 2022 | — |
Code enforcement Building Inspection · CES | May 26, 2022 | May 26, 2022 | — |
Building inspector Building Inspection · BID-INSP | May 26, 2022 | May 26, 2022 | Approved |
Zoning review Planning · CP-ZOC | May 31, 2022 | Feb 14, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 31, 2022 | Apr 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Feb 23, 2023 | Sep 18, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2023 | Sep 8, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 23, 2023 | Apr 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2023 | Mar 1, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 24, 2023 | Feb 27, 2023 | — |
Fire prevention review Fire Department · SFFD | May 8, 2023 | Aug 25, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2023 | Sep 8, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 14, 2023 | Sep 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 14, 2023 | Sep 15, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2023 | Sep 18, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 14, 2023 | Sep 27, 2023 | Approved |
Building inspector Building Inspection · BID-INSP | Sep 27, 2023 | Mar 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 1, 2024 | Apr 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Stephen Antonaros Stephen Antonaros Arch. | Architect | C-14386 |
| Rodrigo Santos | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022