875 A 36th Av
San Francisco permit 202205265050 · Outer Richmond
Legalize (e) non-permitted ground floor unit per state adu program change of occupancy r-3 to r-2. unit will be added per government code section 65852.2 for the state adu program.
- Filed
- May 26, 2022
- Issued
- Jan 24, 2025 (32 months after filing)
- Completed
- May 1, 2025 (3 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 42 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department
- Put on hold
- 8 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2022 | Jun 17, 2022 | Administrative |
Zoning review Planning · CP-ZOC | Jun 17, 2022 | Jun 26, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 17, 2022 | Jan 7, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 23, 2022 | Jan 25, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2022 | Jan 27, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2022 | May 23, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2022 | Jan 26, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2022 | Jan 26, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 25, 2023 | Jan 31, 2023 | — |
Building plan review Building Inspection · BLDG | May 17, 2023 | Jul 13, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 17, 2023 | Dec 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 17, 2023 | May 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 17, 2023 | May 19, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 17, 2023 | May 18, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2023 | Nov 20, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 15, 2023 | Dec 21, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 15, 2023 | Jan 5, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Dec 15, 2023 | Nov 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2023 | Dec 19, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 18, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2023 | Dec 26, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 6, 2024 | Jan 6, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jul 26, 2024 | Jul 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 26, 2024 | Aug 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 26, 2024 | Aug 1, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 26, 2024 | Jul 26, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 26, 2024 | Aug 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 22, 2024 | Aug 26, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 22, 2024 | Aug 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 22, 2024 | Aug 27, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2024 | Aug 23, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2024 | Aug 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2024 | Nov 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 4, 2024 | Nov 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 4, 2024 | Nov 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 4, 2024 | Nov 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 13, 2024 | Nov 15, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 17, 2024 | Dec 17, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Dec 18, 2024 | Dec 18, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2024 | Jan 24, 2025 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2024 | Dec 31, 2024 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $28,261
| Name | Role | License on permit |
|---|---|---|
| Erik Stanton Chan Lun Chan Associates | Architect | C24663 |
| Jesse Eugene Landers Design Everest | Engineer | C83060 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025