3150 California St
San Francisco permit 202205265118 · Presidio Heights
Erect a 3 story with one basement, type 3b, education building containing a mix of science and general education classrooms, a maker space, a student center, faculty and staff offices, food service and athletic facilities. proposed demolition work shown here is to be filed under a stand alone permit
- Filed
- May 26, 2022
- Issued
- Mar 31, 2023 (10 months after filing)
- Completed
- Aug 7, 2025 (28 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 147 stops across 7 departments
- Comments issued
- 19 times, by Building Inspection, Fire Department, Public Works, Public Health
- Put on hold
- 19 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 26, 2022 | May 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | May 31, 2022 | Mar 23, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 1, 2022 | Jun 22, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2022 | Aug 9, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2022 | Mar 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2022 | Mar 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2022 | Jan 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2022 | Oct 3, 2022 | — |
Public health review Public Health · HEALTH | Jun 23, 2022 | Nov 21, 2022 | — |
Public Health HEALTH-HM | Jun 23, 2022 | Jun 28, 2022 | — |
Public health food review Public Health · HEALTH-FD | Jun 27, 2022 | Jul 20, 2022 | — |
Zoning review Planning · CP-ZOC | Jan 9, 2023 | Mar 7, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 23, 2023 | Feb 15, 2023 | — |
Urban forestry Public Works · DPW-BUF | Feb 1, 2023 | Feb 2, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 3, 2023 | Mar 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2023 | Mar 22, 2023 | — |
Public health review Public Health · HEALTH | Mar 3, 2023 | Mar 3, 2023 | — |
Public Health HEALTH-HM | Mar 3, 2023 | Mar 6, 2023 | — |
Public health food review Public Health · HEALTH-FD | Mar 3, 2023 | Mar 6, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 3, 2023 | Mar 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2023 | Mar 8, 2023 | — |
Development fee collection Building Inspection · DFCU | Mar 22, 2023 | Mar 22, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 23, 2023 | Mar 31, 2023 | — |
Addendum 1: Health - maher
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Mar 31, 2023 | Mar 31, 2023 | — |
Public health review Public Health · HEALTH | Mar 31, 2023 | Apr 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Mar 31, 2023 | Apr 10, 2023 | — |
Public health review Public Health · HEALTH | Apr 4, 2023 | Apr 10, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 10, 2023 | Apr 13, 2023 | — |
Addendum 2: Shoring & excavation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 7, 2023 | Apr 7, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2023 | Jul 11, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2023 | Jul 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 7, 2023 | Jul 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 3, 2023 | Jul 13, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 11, 2023 | Jul 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 18, 2023 | Jul 19, 2023 | — |
Addendum 3: Foundation, superstructure, underground utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 7, 2023 | Apr 7, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2023 | Aug 22, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2023 | Aug 28, 2023 | Approved-Stipulated |
Permit Processing Center Building Inspection · PPC | Apr 7, 2023 | Aug 30, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 24, 2023 | Aug 24, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 30, 2023 | Sep 22, 2023 | Administrative |
Addendum 4: Arch, civil, landscape, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Apr 26, 2023 | Apr 26, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2023 | Jul 31, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 26, 2023 | Sep 5, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 26, 2023 | Jul 29, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 26, 2023 | Sep 26, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 26, 2023 | Sep 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 26, 2023 | May 4, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 26, 2023 | Jul 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 26, 2023 | Jan 2, 2024 | Administrative |
Electrical plan review Building Inspection · MECH-E | May 1, 2023 | Sep 18, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 30, 2023 | Sep 11, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2023 | Sep 5, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 11, 2023 | Sep 11, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2023 | Sep 26, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 15, 2023 | Nov 20, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 16, 2023 | Nov 16, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 20, 2023 | Nov 20, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 27, 2023 | Nov 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 27, 2023 | Nov 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 29, 2023 | Dec 1, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Dec 14, 2023 | Dec 14, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Dec 24, 2023 | Dec 24, 2023 | Approved |
Electrical plan review Building Inspection · MECH-E | Dec 27, 2023 | Dec 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 27, 2023 | Dec 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 27, 2023 | Dec 29, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2024 | Jan 4, 2024 | Administrative |
Addendum 5: Puc & dbi-pic: final stormwater control plan
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 12, 2023 | Sep 12, 2023 | Administrative |
Permit Processing Center Building Inspection · PPC | Sep 12, 2023 | Dec 15, 2023 | In Progress |
Plumbing plan check Building Inspection · PID-PC | Sep 15, 2023 | Nov 9, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 9, 2023 | Dec 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 15, 2023 | Dec 26, 2023 | Administrative |
Addendum 6: Metal stairs.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 30, 2024 | Feb 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2024 | Feb 8, 2024 | Administrative |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 1, 2024 | Feb 1, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Feb 6, 2024 | Feb 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 8, 2024 | Feb 12, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 8, 2024 | Mar 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 8, 2024 | Mar 4, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 8, 2024 | Apr 23, 2024 | In Progress |
Fire prevention review Fire Department · SFFD | Mar 4, 2024 | Mar 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 9, 2024 | Apr 9, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 9, 2024 | Apr 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 9, 2024 | Apr 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 12, 2024 | Apr 12, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 23, 2024 | May 1, 2024 | Administrative |
Addendum 7: Fire sprinkler.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 2, 2024 | Feb 8, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Feb 7, 2024 | Feb 7, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Feb 8, 2024 | Feb 8, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Feb 15, 2024 | Feb 15, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 15, 2024 | Mar 25, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 15, 2024 | Jul 2, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 5, 2024 | Jun 5, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 28, 2024 | Jun 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 1, 2024 | Jul 1, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 2, 2024 | Jul 2, 2024 | Administrative |
Addendum 8: Fire alarm & two-way communication system.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 6, 2024 | Mar 14, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 11, 2024 | Mar 18, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Mar 13, 2024 | Mar 13, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Mar 19, 2024 | Apr 1, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | Jul 19, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jun 4, 2024 | Jun 14, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 5, 2024 | Jul 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 19, 2024 | Jul 24, 2024 | Administrative |
Addendum 9: Errcs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 7, 2024 | May 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 21, 2024 | May 21, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2024 | May 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2024 | May 22, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | May 22, 2024 | Jul 3, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 22, 2024 | Jul 23, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Jul 18, 2024 | Jul 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 23, 2024 | Aug 1, 2024 | Administrative |
Addendum 10: Dph - food service.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 22, 2024 | Aug 1, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 30, 2024 | Jul 30, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 30, 2024 | Jul 30, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 31, 2024 | Jul 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2024 | Aug 1, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Aug 1, 2024 | Aug 9, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2024 | Aug 29, 2024 | Issued Comments |
Public health review Public Health · HEALTH | Aug 1, 2024 | Aug 12, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 1, 2024 | Dec 12, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Aug 7, 2024 | Aug 7, 2024 | Approved |
Public health review Public Health · HEALTH | Aug 12, 2024 | Aug 12, 2024 | Administrative |
Public health review Public Health · HEALTH | Dec 4, 2024 | Dec 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 9, 2024 | Dec 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 12, 2024 | Dec 18, 2024 | Administrative |
Addendum 11: Solar pv.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 17, 2024 | Jul 25, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 24, 2024 | Jul 24, 2024 | Not Applicable |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 24, 2024 | Jul 24, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Jul 25, 2024 | Jul 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | Jul 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jul 25, 2024 | Sep 4, 2024 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Jul 25, 2024 | Aug 15, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 25, 2024 | Oct 4, 2024 | — |
Permit Processing Center Building Inspection · PPC | Jul 25, 2024 | Nov 14, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 4, 2024 | Oct 4, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 4, 2024 | Approved |
Electrical plan review Building Inspection · MECH-E | Nov 4, 2024 | Nov 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 4, 2024 | Nov 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2024 | Nov 15, 2024 | Administrative |
Addendum 12: Emergency evacuation maps
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 17, 2025 | Jan 31, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 31, 2025 | Jan 31, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Jan 31, 2025 | Feb 21, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jan 31, 2025 | Feb 28, 2025 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 27, 2025 | Feb 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 28, 2025 | Mar 25, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Complete
- Estimated cost
- $23,500,000
| Name | Role | License on permit |
|---|---|---|
| J Aaron Thornton Leddy Maytum Stacy Architects | Architect | C35066 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022