225 Edgehill Wy
San Francisco permit 202205275125 · West of Twin Peaks
Partial replacement, in kind of (e)hipped roof reframing at rear of building (north + north east elevation) front door replacement. window replacements. window replacements at rear and weat side (no impact on public right of way). interior renovation of existing kitchen including removal of interior
- Filed
- May 27, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 6 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | May 27, 2022 | May 27, 2022 | — |
Zoning review Planning · CP-ZOC | May 27, 2022 | In progress | — |
Central Permit Bureau Building Inspection · CPB | Jun 9, 2022 | Jun 9, 2022 | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Withdrawn
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Jason Park Langkammerer At6 Architecture Design | Architect | C28796 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026