66 Gladstone Dr
San Francisco permit 202205275127 · Excelsior
(n) 1 bedrm, 1 bath adu at lower level. main home remodel & addition. upper level work includes (n) bathroom, office/bedroom, & stairs. lower level work includes (n) laundry area. front yard work, (n) patio & entryway for adu, replace (e) driveway w/ permeable paving.
- Filed
- May 27, 2022
- Issued
- Sep 22, 2023 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 7 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 27, 2022 | Nov 22, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 22, 2022 | Jun 29, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 22, 2022 | Aug 10, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2022 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2022 | Jun 29, 2023 | — |
Urban forestry Public Works · DPW-BUF | Nov 22, 2022 | Aug 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 22, 2022 | Aug 9, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 22, 2022 | Sep 14, 2023 | In Progress |
Planning neighborhood notice Planning · CP-NP | Mar 22, 2023 | Aug 10, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jun 28, 2023 | Aug 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 29, 2023 | Jun 29, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 29, 2023 | Aug 10, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2023 | Aug 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2023 | Aug 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 12, 2023 | Sep 12, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 13, 2023 | Sep 14, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Sep 13, 2023 | Sep 13, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 14, 2023 | Sep 22, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $312,000
| Name | Role | License on permit |
|---|---|---|
| Juan Bautista Aleman Hernandez Tangobuilder | Engineer | C86746 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025