1212 Union St
San Francisco permit 202205315292 · Russian Hill
Expansion of 3rd floor towards the south property line w/ (n) stair to roof. project to include an alteration of the facade @ 3rd level only. new windows, doors, electrical & plumbing work as required for the above scope.
- Filed
- May 31, 2022
- Issued
- Apr 16, 2025 (35 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 55 stops across 6 departments
- Comments issued
- 17 times, by Building Inspection, Public Utilities, Fire Department, Public Works
- Put on hold
- Once
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 2, 2022 | Jun 2, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 2, 2022 | Jun 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 2, 2022 | Apr 7, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 16, 2022 | Nov 6, 2024 | Approved |
Planning neighborhood notice Planning · CP-NP | Feb 21, 2023 | May 10, 2023 | Approved |
Planning discretionary review Planning · CP-DR | May 9, 2023 | Nov 10, 2023 | Not Applicable |
Building plan review Building Inspection · BLDG | Nov 6, 2024 | Dec 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2024 | Nov 7, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 6, 2024 | Jan 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2025 | Jan 13, 2025 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Jan 9, 2025 | Jan 10, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 10, 2025 | Jan 27, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 20, 2025 | Feb 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 20, 2025 | Feb 24, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 20, 2025 | Feb 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 20, 2025 | Feb 24, 2025 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 4, 2025 | Apr 16, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 12, 2025 | Mar 13, 2025 | Approved |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 6, 2025 | Jun 18, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 18, 2025 | Jun 23, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Jun 23, 2025 | Jun 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 23, 2025 | Aug 22, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 23, 2025 | Aug 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2025 | Jul 25, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 23, 2025 | Jun 26, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2025 | Jun 27, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2025 | Jun 26, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 23, 2025 | Sep 10, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 5, 2025 | Sep 8, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Sep 5, 2025 | Sep 5, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 2, 2025 | Dec 3, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 9, 2025 | Dec 9, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 12, 2026 | Jan 16, 2026 | Approved |
Building plan review Building Inspection · BLDG | Feb 26, 2026 | Mar 20, 2026 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 10, 2026 | Mar 10, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 16, 2026 | Mar 16, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 20, 2026 | May 4, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 2, 2026 | Apr 7, 2026 | Approved |
Building plan review Building Inspection · BLDG | Apr 8, 2026 | May 15, 2026 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Apr 30, 2026 | May 4, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | May 1, 2026 | May 1, 2026 | Approved |
Fire prevention review Fire Department · SFFD | May 4, 2026 | May 4, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 15, 2026 | May 22, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | May 22, 2026 | May 22, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Jul 9, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2026 | Aug 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 5, 2026 | Aug 5, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 18, 2026 | Aug 31, 2026 | Approved |
Zoning review Planning · CP-ZOC | Aug 31, 2026 | Sep 10, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 31, 2026 | Aug 31, 2026 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 31, 2026 | Sep 10, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Aug 31, 2026 | Sep 4, 2026 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 31, 2026 | Sep 2, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 31, 2026 | Sep 4, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 10, 2026 | Sep 21, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $297,432
| Name | Role | License on permit |
|---|---|---|
| Andrew Johnston Rodgers Rodgers Architecture | Architect | C30697 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2021