603 San Bruno Av
San Francisco permit 202206025520 · Potrero Hill
Remodel & addition to (e) sfh. proposed includes total of (2) units (+1 adu under separate permit). lvl 1 5'-0" rear yard addition (new adu at lvl 1 under sep. permit unit c). remodel (e) 2nd lvl +5'-0" rear yard addition (unit a). new lvl 3 (unit b).
- Filed
- Jun 2, 2022
- Issued
- Feb 15, 2024 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 38 stops across 5 departments
- Comments issued
- 8 times, by Permit Center, Building Inspection, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 2, 2022 | Jun 13, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 13, 2022 | Apr 4, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 13, 2022 | Jan 9, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Feb 10, 2023 | Apr 5, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 5, 2023 | Dec 21, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 5, 2023 | May 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 5, 2023 | Apr 5, 2023 | — |
Zoning review Planning · CP-ZOC | Dec 20, 2023 | Dec 28, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Jan 8, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Jan 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Dec 27, 2023 | Jan 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 9, 2024 | Feb 15, 2024 | Administrative |
Addendum 1: Foundation/t24/mech/elec/final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 22, 2024 | Apr 1, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Mar 25, 2024 | Mar 25, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 28, 2024 | Mar 28, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 1, 2024 | Apr 1, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 3, 2024 | Apr 9, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 8, 2024 | Apr 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 9, 2024 | Apr 16, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Apr 16, 2024 | May 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 16, 2024 | Apr 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 16, 2024 | Apr 17, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 16, 2024 | Apr 18, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 16, 2024 | Nov 20, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Apr 17, 2024 | May 15, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 9, 2024 | May 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2024 | Aug 14, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 24, 2024 | Nov 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2024 | Jul 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2024 | Jul 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 10, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 4, 2024 | Sep 17, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 4, 2024 | Sep 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2024 | Sep 9, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Sep 17, 2024 | Sep 18, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Nov 6, 2024 | Nov 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 13, 2024 | Nov 20, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $711,000
| Name | Role | License on permit |
|---|---|---|
| Andrea Gabriele Cernusak Andrea Cernusak Architect | Architect | C-33206 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023