33 Lincoln Wy
San Francisco permit 202206075806 · Inner Sunset
Vertical one story addition includes 3 bedrooms and 2 bathrooms. new interior stair from 3rd fl. new exterior patio & exterior stair to new roof deck.
- Filed
- Jun 7, 2022
- Issued
- Dec 5, 2023 (18 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 62 stops across 5 departments
- Comments issued
- 15 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 7, 2022 | Jun 27, 2022 | Administrative |
Zoning review Planning · CP-ZOC | Jun 27, 2022 | May 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 27, 2022 | Nov 27, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Mar 29, 2023 | May 23, 2023 | — |
Building plan review Building Inspection · BLDG | May 23, 2023 | Oct 26, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2023 | Aug 3, 2023 | Approved |
Fire prevention review Fire Department · SFFD | May 23, 2023 | Sep 5, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 23, 2023 | May 30, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 23, 2023 | Aug 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2023 | Aug 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2023 | Aug 24, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Sep 27, 2023 | Sep 28, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 27, 2023 | Oct 4, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 27, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 27, 2023 | Sep 29, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 5, 2023 | Oct 6, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 2, 2023 | Nov 13, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 2, 2023 | Nov 27, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 2, 2023 | Nov 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 2, 2023 | Nov 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Nov 3, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 6, 2023 | Nov 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 13, 2023 | Nov 13, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 15, 2023 | Nov 16, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2023 | Dec 5, 2023 | Administrative |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 22, 2023 | Jan 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 10, 2024 | Feb 22, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 10, 2024 | Mar 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 10, 2024 | Feb 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 10, 2024 | Apr 30, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 10, 2024 | Feb 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 10, 2024 | Jan 19, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 10, 2024 | Dec 9, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Feb 2, 2024 | Apr 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Apr 29, 2024 | May 8, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 29, 2024 | May 30, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 29, 2024 | May 13, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 29, 2024 | May 2, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Apr 29, 2024 | Apr 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 31, 2024 | May 31, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 4, 2024 | Jun 4, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 7, 2024 | Jun 7, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 23, 2024 | Aug 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 23, 2024 | Aug 6, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jul 23, 2024 | Nov 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 23, 2024 | Jul 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 23, 2024 | Jul 23, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 23, 2024 | Oct 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 23, 2024 | Jul 26, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 17, 2024 | Oct 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2024 | Oct 30, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2024 | Oct 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Oct 17, 2024 | Oct 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2024 | Oct 18, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2024 | Nov 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 12, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2024 | Nov 12, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2024 | Nov 13, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 12, 2024 | Nov 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2024 | Nov 13, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 20, 2024 | Dec 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 9, 2024 | Dec 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $599,500
| Name | Role | License on permit |
|---|---|---|
| Johanna Clare Street Johanna Street Architect | Architect | C30268 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026