San Francisco permit 202206075820 · Noe Valley

AdditionFull plan reviewComplete
Street view · Feb 2022
Google Street View of 320 Day St, Feb 2022
Scope of work
As written on the permit application.

Remodel of existing two story residence.horizontal addition in rear.

Timeline
Key dates from the city record.
Filed
Jun 7, 2022
Issued
Jan 29, 2024 (20 months after filing)
Completed
Mar 20, 2025 (14 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
55 stops across 6 departments
Comments issued
4 times, by Permit Center, Building Inspection
Put on hold
Twice

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 7, 2022—

Apartment and hotel inspection

Building Inspection · HIS

Jul 5, 2022—

Code enforcement

Building Inspection · CES

Jul 5, 2022—

Building inspector

Building Inspection · BID-INSP

Jul 5, 2022—

Permit Processing Center

Building Inspection · PPC

Jan 23, 2024—

Zoning review

Planning · CP-ZOC

Dec 28, 2022—

Planning neighborhood notice

Planning · CP-NP

Dec 28, 2022—

Building plan review

Building Inspection · BLDG

Mar 6, 2023—

Street use and mapping

Public Works · DPW-BSM

Jan 11, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 10, 2023—

Fire prevention review

Fire Department · SFFD

Apr 10, 2023—

Fire prevention review

Fire Department · SFFD

Jun 20, 2023—

Zoning review

Planning · CP-ZOC

Apr 5, 2023—

Building plan review

Building Inspection · BLDG

Mar 30, 2023—

Street use and mapping

Public Works · DPW-BSM

Dec 27, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 30, 2023—

Building plan review

Building Inspection · BLDG

Apr 14, 2023—

Zoning review

Planning · CP-ZOC

Jun 9, 2023—

Building plan review

Building Inspection · BLDG

Jun 15, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 15, 2023—

Zoning review

Planning · CP-ZOC

Jun 22, 2023—

Building plan review

Building Inspection · BLDG

Jun 15, 2023—

Zoning review

Planning · CP-ZOC

Jun 27, 2023—

Building plan review

Building Inspection · BLDG

Jul 6, 2023Approved

Fire prevention review

Fire Department · SFFD

Aug 21, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 11, 2023—

Building plan review

Building Inspection · BLDG

Nov 8, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 2, 2023Approved

Fire prevention review

Fire Department · SFFD

Nov 3, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 17, 2023Approved

Permit Center

Permit Center · PERMIT-CTR

Dec 22, 2023—

Street use and mapping

Public Works · DPW-BSM

Jan 18, 2024Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Jan 29, 2024Administrative

Addendum 1: Final

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Mar 1, 2024Issued Comments

Mechanical pre-screening

Building Inspection · PRE-MECH

Feb 22, 2024Issued Comments

Electrical pre-screening

Building Inspection · PRE-MECH-E

Feb 29, 2024Not Applicable

Building pre-screening

Building Inspection · PRE-BLDG

Mar 1, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Mar 21, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Mar 20, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 22, 2024Administrative

Building plan review

Building Inspection · BLDG

May 20, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Apr 30, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Mar 28, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 26, 2024Approved

Permit Processing Center

Building Inspection · PPC

Jul 22, 2024Administrative

Mechanical and energy plan review

Building Inspection · MECH

Jun 21, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 21, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 9, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 26, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 15, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 15, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 16, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jul 24, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$547,699
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Alfonso Kirkpatrick Fillon

Fillon Design

ArchitectC28828
Albert Urrutia

Atrium Structural Engineer

EngineerS2994
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202206075820 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record