4052 25th St
San Francisco permit 202206085874 · Noe Valley
New 113 sq ft at 3rd floor for new bath & dressing by changing roof height within footprint & setbacks. new powder room, closet & stair configuration on 2nd floor. no change to 1st floor or number of plumbing fixture.
- Filed
- Jun 8, 2022
- Issued
- Aug 9, 2023 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 9, 2022 | Jun 9, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 9, 2022 | Mar 8, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jan 9, 2023 | Jan 24, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 9, 2023 | May 8, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 8, 2023 | Jun 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 7, 2023 | Jun 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 7, 2023 | Aug 9, 2023 | Administrative |
Addendum 1: Architectural, t-24, structural, final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 14, 2023 | Aug 14, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 14, 2023 | Sep 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 20, 2023 | Oct 18, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2023 | Oct 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2023 | Nov 9, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Zoning review Planning · CP-ZOC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Donna Leigh Schumacher Dsa | Architect | C-23503 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2023