665 Alvarado St
San Francisco permit 202206085903 · Noe Valley
Respond to complaint 2019-022212enf - construct stepped retaining wall to restore the rear yard to similar condition prior to the complaint; construct new stair as require for yard access due to stepped retaining wall
- Filed
- Jun 8, 2022
- Issued
- Jan 12, 2024 (19 months after filing)
- Completed
- Jun 24, 2024 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 6 stops across 2 departments
- Comments issued
- None
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 8, 2022 | Jun 8, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 8, 2022 | Jun 8, 2022 | — |
Intake Building Inspection · INTAKE | Jan 18, 2023 | Jan 18, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 18, 2023 | Jan 18, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 18, 2023 | Jan 18, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2024 | Jan 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $15,000
| Name | Role | License on permit |
|---|---|---|
| Julia Yung-Ling Chen Julia Y. Chen Design Inc. | Engineer | S4498 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2022