945 Market St
San Francisco permit 202206106082 · South of Market
Exterior scope of work: new windows on level 4 along stevenson. interior scope of work: new structural pedestrian bridge at level 2; non-structual partions; door updates; lighting upgrades; architectural finish refresh; accessibility upgrades; signage updates.
- Filed
- Jun 10, 2022
- Issued
- Jul 10, 2023 (13 months after filing)
- Completed
- Feb 11, 2025 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 25 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 14 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 10, 2022 | Jun 21, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2022 | Jul 7, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2022 | Jul 7, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 5, 2022 | Mar 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2022 | Feb 22, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Sep 19, 2022 | Jan 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Sep 19, 2022 | Jun 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 19, 2022 | Nov 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2022 | Apr 26, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jan 30, 2023 | Apr 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 27, 2023 | Jun 23, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 28, 2023 | Apr 26, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 26, 2023 | May 1, 2023 | — |
Building plan review Building Inspection · BLDG | May 15, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | May 19, 2023 | May 19, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 5, 2023 | Jun 22, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 22, 2023 | Jun 23, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 23, 2023 | Jun 27, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 26, 2023 | Jul 6, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Jun 26, 2023 | Jun 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2023 | Jun 26, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 26, 2023 | Jun 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 30, 2023 | Jun 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Jul 6, 2023 | Jul 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 7, 2023 | Jul 10, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $10,600,000
| Name | Role | License on permit |
|---|---|---|
| Barry J Bourbon Gensler Architects | Architect | C25873 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026