1360 Fairfax Av
San Francisco permit 202206156446 · Bayview Hunters Point
T.i. with (n) demising wall and ada toilet for lease space s-3 occupancy. t.i. for canine enrichment with mep and (n) ada toilet for change of use from s-2 to b. (n) exterior roll up doors to access (e) side yard. repair (e) roof.
- Filed
- Jun 15, 2022
- Issued
- Aug 23, 2022 (2 months after filing)
- Completed
- Jun 23, 2023 (10 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 12 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 15, 2022 | Jun 15, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 16, 2022 | Jun 16, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2022 | Aug 18, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 22, 2022 | Jun 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 22, 2022 | Jun 22, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jun 23, 2022 | Jun 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Jun 23, 2022 | Jun 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2022 | Jun 23, 2022 | — |
Public health review Public Health · HEALTH | Jun 23, 2022 | Jun 23, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jul 29, 2022 | Jul 29, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 19, 2022 | Aug 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 23, 2022 | Aug 23, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Karen F Curtiss Red Dot Studio Architecture | Architect | C31453 |
| Nilgun Asci Wolpe Ny Engineering Consulting | Engineer | 68482 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026