10 South Van Ness Av
San Francisco permit 202206176565 · Mission
Erect 55-stories over 2-basement, mixed use residential building with 966 dwelling units, retail and services use, and parking. (r-2,m,a-2,a-3,s-2). project will includer merger of lots 004 and 003a on block 3506. maher ord 155-13 applies.
- Filed
- Jun 17, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 37 stops across 7 departments
- Comments issued
- 9 times, by Fire Department, Public Utilities, Public Health, CON, Building Inspection
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 17, 2022 | Jun 21, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2022 | In progress | — |
Permit Processing Center Building Inspection · PPC | Jun 21, 2022 | In progress | In Progress |
Building plan review Building Inspection · BLDG | Aug 23, 2022 | Jan 5, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Aug 23, 2022 | Jan 29, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2022 | Jun 8, 2026 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2022 | Aug 26, 2022 | Issued Comments |
Public health review Public Health · HEALTH | Aug 23, 2022 | Mar 28, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 23, 2023 | Jan 5, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 27, 2026 | Jun 10, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | May 27, 2026 | Jun 22, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | May 27, 2026 | Jul 13, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 27, 2026 | Jun 8, 2026 | Approved-Stipulated |
Public health review Public Health · HEALTH | May 27, 2026 | May 29, 2026 | Approved |
CON CON-BOND | May 27, 2026 | May 28, 2026 | Issued Comments |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jun 1, 2026 | Jun 11, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jun 8, 2026 | Jun 22, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jun 10, 2026 | Jun 22, 2026 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jun 10, 2026 | Jun 17, 2026 | Approved-Stipulated |
Public health review Public Health · HEALTH | Jun 10, 2026 | Jun 12, 2026 | Approved |
Public Health HEALTH-AW | Jun 12, 2026 | Jun 12, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Jun 22, 2026 | Jun 22, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Jul 9, 2026 | Aug 17, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 9, 2026 | Aug 17, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 9, 2026 | Jul 13, 2026 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 9, 2026 | Aug 19, 2026 | Approved-Stipulated |
Public Utilities programs review Public Utilities · SFPUC-PRG | Jul 9, 2026 | Aug 13, 2026 | Approved |
Public health review Public Health · HEALTH | Jul 9, 2026 | Jul 10, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 30, 2026 | Jul 30, 2026 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 19, 2026 | Aug 19, 2026 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
CON CON-BOND | — | In progress | — |
Development fee collection Building Inspection · DFCU | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Filed
- Estimated cost
- $430,000,000
| Name | Role | License on permit |
|---|---|---|
| Charles Yancey Clayton Ibi Group | Architect | C-35502 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026