239 Molimo Dr
San Francisco permit 202206176591 · West of Twin Peaks
Demo extg stair from 2nd floor to the 1st floor. construct new stairs. demo extg posts and beams on 1st floor. replace per structural design. new window and door, new full bath and extended framing and new retaining walls on 1st floor. new family room and office at 1st floor - new conditioned space
- Filed
- Jun 17, 2022
- Issued
- Jan 26, 2023 (7 months after filing)
- Completed
- Sep 4, 2024 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 14 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 17, 2022 | Jun 17, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2022 | Aug 8, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 4, 2022 | Aug 4, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 4, 2022 | Aug 4, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2022 | Aug 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 8, 2022 | Aug 8, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 16, 2022 | Dec 8, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Oct 13, 2022 | Oct 13, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2022 | Oct 25, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 8, 2022 | Dec 8, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 9, 2022 | Jan 11, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 12, 2023 | Jan 12, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 12, 2023 | Jan 12, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jan 12, 2023 | Jan 26, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $95,000
| Name | Role | License on permit |
|---|---|---|
| Kamala L Mostert Mostert Architecture | Architect | C26896 |
| Albert Urrutia Atrium Structural Engineers | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2014