2301 Chestnut St
San Francisco permit 202206216759 · Marina
Tenant improvement of an (e) vacant space to support a (n) restaurant. scope to include mechanical, electrical, plumbing, and minor structural to support rooftop mechanical equipment and construction of stall storage mezzanine.
- Filed
- Jun 21, 2022
- Issued
- Dec 2, 2022 (5 months after filing)
- Completed
- Jul 3, 2024 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 18 stops across 7 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 6 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 21, 2022 | Jun 21, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 23, 2022 | Jun 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2022 | Jun 23, 2022 | — |
Intake Building Inspection · INTAKE | Jul 1, 2022 | Jul 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Jul 1, 2022 | Jul 1, 2022 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2022 | Jul 6, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Jul 6, 2022 | Jul 6, 2022 | — |
Public health review Public Health · HEALTH | Jul 6, 2022 | Nov 18, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 13, 2022 | Jul 14, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Jul 13, 2022 | Jul 13, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 19, 2022 | Jul 25, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 26, 2022 | Jul 26, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2022 | Nov 16, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 26, 2022 | Nov 21, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 13, 2022 | Nov 17, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 16, 2022 | Nov 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 22, 2022 | Nov 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 23, 2022 | Dec 2, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $850,000
| Name | Role | License on permit |
|---|---|---|
| Kurt Edward Simrock Arcanum Arch. | Architect | C24259 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025