4945 Anza St
San Francisco permit 202206216776 · Outer Richmond
To comply with nov# 2020058331. legalization of 2nd per density unit at 1st level. legalize rear stairs. new read door an balcony @ 2nd level.
- Filed
- Jun 21, 2022
- Issued
- Apr 16, 2024 (22 months after filing)
- Completed
- Mar 11, 2025 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 36 stops across 6 departments
- Comments issued
- 6 times, by Building Inspection, Public Works, Fire Department
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 21, 2022 | Jun 21, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 22, 2022 | May 11, 2023 | — |
Building plan review Building Inspection · BLDG | May 12, 2023 | Sep 19, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2023 | Jun 13, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 13, 2023 | Aug 7, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 17, 2023 | Dec 15, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 6, 2023 | Oct 6, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 6, 2023 | Dec 26, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 26, 2023 | Dec 28, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Dec 28, 2023 | Jan 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2024 | Jan 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jan 24, 2024 | Jan 24, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2024 | Jan 26, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 29, 2024 | Feb 27, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 28, 2024 | Mar 6, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2024 | Apr 16, 2024 | Administrative |
Addendum 1: Struct,arch,t-24,mep,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 22, 2024 | Apr 29, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 26, 2024 | Apr 26, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Apr 29, 2024 | Apr 29, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 29, 2024 | Apr 29, 2024 | Not Applicable |
Central Permit Bureau Building Inspection · CPB | Apr 30, 2024 | May 2, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 2, 2024 | May 21, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 2, 2024 | May 12, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 2, 2024 | May 8, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 2, 2024 | May 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2024 | May 8, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 2, 2024 | Jun 4, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 29, 2024 | May 31, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 29, 2024 | May 31, 2024 | Approved |
Fire prevention review Fire Department · SFFD | May 29, 2024 | May 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 29, 2024 | May 29, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 30, 2024 | Jun 6, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 30, 2024 | Jun 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 30, 2024 | Jun 4, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 4, 2024 | Jun 12, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $160,000
| Name | Role | License on permit |
|---|---|---|
| Andrea Gabriele Cernusak Andrea Cernusak | Architect | C33206 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017