1778 48th Av
San Francisco permit 202206236949 · Sunset/Parkside
New 200 sqft accessory structure on the backyard for office/gym.
- Filed
- Jun 23, 2022
- Issued
- Jan 10, 2024 (19 months after filing)
- Completed
- Jul 25, 2024 (6 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 21 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Planning
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 23, 2022 | Sep 12, 2022 | Administrative |
Zoning review Planning · CP-ZOC | Sep 12, 2022 | Feb 21, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 12, 2022 | Jan 3, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Dec 19, 2022 | Feb 21, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 23, 2023 | Apr 24, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 23, 2023 | Oct 16, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Feb 23, 2023 | May 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 23, 2023 | Mar 1, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 31, 2023 | Nov 10, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 31, 2023 | Oct 31, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 31, 2023 | Oct 31, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 31, 2023 | Oct 31, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2023 | Dec 26, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 30, 2023 | Dec 13, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Nov 30, 2023 | Nov 30, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 7, 2023 | Dec 7, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 21, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 27, 2023 | Jan 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Dec 27, 2023 | Dec 27, 2023 | Administrative |
Development fee collection Building Inspection · DFCU | Jan 3, 2024 | Jan 3, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 3, 2024 | Jan 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $110,000
| Name | Role | License on permit |
|---|---|---|
| David N Marlatt Dnm Architect | Architect | C27909 |
| Erik Garcia Wm Structural Engineering | Engineer | C87465 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2014