961 De Haro St
San Francisco permit 202206237003 · Potrero Hill
Erect a 4-story, type 5a, two residential units building with one basement level on southern half of (e) lot.
- Filed
- Jun 23, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 27 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Utilities
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 23, 2022 | Jun 27, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 27, 2022 | Nov 6, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Jun 27, 2022 | May 8, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | May 3, 2023 | May 11, 2023 | — |
Planning discretionary review Planning · CP-DR | Jun 30, 2023 | Jul 3, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 7, 2023 | Dec 20, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 7, 2023 | Jan 19, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 7, 2023 | Nov 8, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2023 | Nov 22, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 18, 2023 | Feb 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 12, 2024 | Jan 30, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Feb 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 27, 2024 | Feb 27, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 29, 2024 | Mar 6, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 8, 2024 | Mar 8, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 15, 2024 | Mar 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 18, 2024 | Mar 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 18, 2024 | Mar 22, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 18, 2024 | Mar 20, 2024 | Approved-Stipulated |
Zoning review Planning · CP-ZOC | Mar 22, 2024 | Mar 22, 2024 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 22, 2024 | Mar 22, 2024 | Administrative |
Fire prevention review Fire Department · SFFD | Mar 28, 2024 | Apr 3, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 28, 2024 | Mar 28, 2024 | Approved |
Zoning review Planning · CP-ZOC | Apr 10, 2024 | Apr 10, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Apr 11, 2024 | Apr 29, 2024 | Approved |
Development fee collection Building Inspection · DFCU | May 3, 2024 | May 3, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 8, 2024 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Approved
- Estimated cost
- $2,000,000
| Name | Role | License on permit |
|---|---|---|
| Owen Cheatham Kennerly Kennerly Architecture | Architect | C29565 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024