436 Eureka St
San Francisco permit 202206287312 · Noe Valley
This permit revises or supplements an earlier permit, so it is not counted in permit totals or timing.
Alter site permit# 2018-1009-2526-s to conform with exhibit 9 of appeal # 22-013 bpa# 2022-0527-5182
- Filed
- Jun 28, 2022
- Issued
- Oct 14, 2022 (4 months after filing)
- Completed
- Not completed yet
- Review stops
- 26 stops across 6 departments
- Comments issued
- 6 times, by Permit Center, Building Inspection, Fire Department, Public Works
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 28, 2022 | Jun 28, 2022 | — |
Zoning review Planning · CP-ZOC | Jun 28, 2022 | Jun 28, 2022 | — |
Building plan review Building Inspection · BLDG | Jun 28, 2022 | Jun 28, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2022 | Jun 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Jun 29, 2022 | Jun 29, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 20, 2022 | Oct 14, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 14, 2022 | Oct 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 14, 2022 | Oct 14, 2022 | — |
Addendum 1: Final - foundation, superstructure, title 24 & mech.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 7, 2025 | Mar 24, 2025 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 14, 2025 | Apr 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 5, 2025 | May 5, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 6, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | May 6, 2025 | Jul 1, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 6, 2025 | Jul 1, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 6, 2025 | Jun 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 6, 2025 | May 15, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | May 6, 2025 | May 8, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | May 6, 2025 | May 16, 2025 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 6, 2025 | May 12, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 6, 2025 | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Urban forestry Public Works · DPW-BUF | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Cancelled
- Estimated cost
- $1
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clark Mcgriff Mcgriff Architects | Architect | C34047 |
| Nicholas C Thomas Thomas Works A+D | Authorized agent-others | C-38546 |
| Jason R Powers Zfa Structural Engineers | Engineer | C-76130 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023