1011 Bryant St #0
San Francisco permit 202206297373 · South of Market
Exterio alterations including (n) rolling over head door; acm cladding interior alterations in customer areas, including tenant improvements in showroom, sales office customer lounge area and public restrooms. minor interior alterations in employee and back of house areas. primarily comprising repla
- Filed
- Jun 29, 2022
- Issued
- Nov 16, 2022 (5 months after filing)
- Completed
- Jan 12, 2024 (14 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 15 stops across 6 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Twice
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jun 29, 2022 | Jun 29, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 18, 2022 | Jul 18, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2022 | Aug 5, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Aug 5, 2022 | Aug 5, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 9, 2022 | Aug 9, 2022 | — |
Public health review Public Health · HEALTH | Aug 9, 2022 | Aug 9, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 9, 2022 | Aug 9, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2022 | Aug 15, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 18, 2022 | Aug 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 19, 2022 | Sep 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 2, 2022 | Sep 7, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 12, 2022 | Nov 8, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 8, 2022 | Nov 9, 2022 | — |
Permit Processing Center Building Inspection · PPC | Nov 9, 2022 | Nov 14, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2022 | Nov 16, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Alan Arthur Cross Proto Inc. | Architect | C30029 |
| Alex Filatov Murphy Burr Curry Inc. | Engineer | C65023 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025