San Francisco permit 202206297373 · South of Market

Commercial or tenant improvementFull plan reviewComplete
Street view · May 2025
Google Street View of 1011 Bryant St #0, May 2025
Scope of work
As written on the permit application.

Exterio alterations including (n) rolling over head door; acm cladding interior alterations in customer areas, including tenant improvements in showroom, sales office customer lounge area and public restrooms. minor interior alterations in employee and back of house areas. primarily comprising repla

Timeline
Key dates from the city record.
Filed
Jun 29, 2022
Issued
Nov 16, 2022 (5 months after filing)
Completed
Jan 12, 2024 (14 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
15 stops across 6 departments
Comments issued
Not recorded for this permit
Put on hold
Twice

The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.

Review stopFinishedResult

Intake

Building Inspection · INTAKE

Jun 29, 2022—

Zoning review

Planning · CP-ZOC

Jul 18, 2022—

Building plan review

Building Inspection · BLDG

Aug 5, 2022—

Electrical plan review

Building Inspection · MECH-E

Aug 5, 2022—

Fire prevention review

Fire Department · SFFD

Aug 9, 2022—

Public health review

Public Health · HEALTH

Aug 9, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 9, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Aug 15, 2022—

Permit Center

Permit Center · PERMIT-CTR

Aug 23, 2022—

Central Permit Bureau

Building Inspection · CPB

Sep 1, 2022—

Fire prevention review

Fire Department · SFFD

Sep 7, 2022—

Electrical plan review

Building Inspection · MECH-E

Nov 8, 2022—

Fire prevention review

Fire Department · SFFD

Nov 9, 2022—

Permit Processing Center

Building Inspection · PPC

Nov 14, 2022—

Central Permit Bureau

Building Inspection · CPB

Nov 16, 2022—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$1,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Alan Arthur Cross

Proto Inc.

ArchitectC30029
Alex Filatov

Murphy Burr Curry Inc.

EngineerC65023
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202206297373 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record