780 Darien Wy
San Francisco permit 202206307477 · West of Twin Peaks
Convert an existing detached garage to an adu unit with a living roof per the state adu program. the project also proposes adding two parking spaces in the existing driveway. to comply with pid complaint #202288002, bid nov #202287234, and planning enf case no. 2022-0674enf.
- Filed
- Jun 30, 2022
- Issued
- Nov 21, 2023 (17 months after filing)
- Completed
- May 15, 2025 (18 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 31 stops across 4 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Planning review Planning · CP-GEN | Jun 30, 2022 | Jun 30, 2022 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jul 19, 2022 | Aug 22, 2022 | — |
Building inspector Building Inspection · BID-INSP | Jul 29, 2022 | Aug 11, 2022 | — |
Electrical inspector Building Inspection · EID-INSP | Jul 29, 2022 | Jul 29, 2022 | — |
Plumbing inspector Building Inspection · PID-INSP | Jul 29, 2022 | Jul 29, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 22, 2022 | Sep 21, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Aug 23, 2022 | Aug 3, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 23, 2022 | Sep 23, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2022 | Aug 25, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 23, 2022 | Sep 21, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 23, 2022 | Sep 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2023 | Aug 3, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 8, 2023 | Aug 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 9, 2023 | Aug 9, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 16, 2023 | Aug 16, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 16, 2023 | Aug 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 16, 2023 | Aug 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 16, 2023 | Aug 24, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Sep 21, 2023 | Sep 21, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 21, 2023 | Nov 21, 2023 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 12, 2023 | Dec 12, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 12, 2023 | Feb 8, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 12, 2023 | Feb 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 12, 2023 | Dec 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2023 | Dec 18, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 12, 2023 | Apr 16, 2024 | — |
Building plan review Building Inspection · BLDG | Apr 3, 2024 | Apr 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2024 | Apr 9, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2024 | Apr 9, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2024 | Apr 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2024 | Apr 17, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $68,948
| Name | Role | License on permit |
|---|---|---|
| Suppayarn Dechpormsuk | Engineer | C84285 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022