144 Laidley St

San Francisco permit 202207017587 · Glen Park

New buildingFull plan reviewIssued
Street view · Nov 2013
Google Street View of 144 Laidley St, Nov 2013
Scope of work
As written on the permit application.

Bldg a: erect 4-story over 1 basement, type 5b, single family dwelling with 1 adu. project to include lot split. (demo under pa# 202207017611. new construction bldg b pa# 202207017622).

Timeline
Key dates from the city record.
Filed
Jul 1, 2022
Issued
Jan 23, 2026 (43 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
49 stops across 6 departments
Comments issued
10 times, by Public Works, Permit Center, Building Inspection, Fire Department, Public Utilities
Put on hold
4 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 27, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 18, 2023—

Zoning review

Planning · CP-ZOC

Aug 12, 2022—

Building plan review

Building Inspection · BLDG

Jun 5, 2023—

Structural plan approval

Building Inspection · PAD-STR

Jun 7, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Sep 2, 2022—

Fire prevention review

Fire Department · SFFD

Jul 31, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 28, 2022—

Urban forestry

Public Works · DPW-BUF

Aug 3, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Mar 16, 2023—

Street use and mapping

Public Works · DPW-BSM

Apr 19, 2023—

Zoning review

Planning · CP-ZOC

Mar 14, 2023—

Zoning review

Planning · CP-ZOC

May 18, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 4, 2023Approved

Urban forestry

Public Works · DPW-BUF

Aug 14, 2023Approved

Development fee collection

Building Inspection · DFCU

Aug 16, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 23, 2026Administrative

Addendum 1: Excavation/shoring

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Feb 24, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Feb 27, 2026Administrative

Building plan review

Building Inspection · BLDG

Mar 30, 2026Approved

Structural plan approval

Building Inspection · PAD-STR

Mar 30, 2026Administrative

Fire Department housing review

Fire Department · SFFD-HQ

Mar 2, 2026Approved-Stipulated

Street use and mapping

Public Works · DPW-BSM

Apr 8, 2026Approved

Urban forestry

Public Works · DPW-BUF

Apr 22, 2026Approved

Permit Processing Center

Building Inspection · PPC

Apr 23, 2026Administrative

Urban forestry

Public Works · DPW-BUF

Apr 22, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Apr 30, 2026Administrative

Addendum 2: Foundation superstructure mep t24

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Apr 21, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

May 12, 2026Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Aug 4, 2026Approved

Central Permit Bureau

Building Inspection · CPB

Aug 6, 2026Administrative

Zoning review

Planning · CP-ZOC

Aug 7, 2026Approved

Building plan review

Building Inspection · BLDG

Sep 4, 2026Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Sep 8, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 19, 2026Issued Comments

Fire Department housing review

Fire Department · SFFD-HQ

Aug 11, 2026Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 11, 2026Approved

Urban forestry

Public Works · DPW-BUF

Sep 9, 2026Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 18, 2026Approved

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 18, 2026Issued Comments

Permit Processing Center

Building Inspection · PPC

In progress—

Public Utilities programs review

Public Utilities · SFPUC-PRG

Aug 18, 2026Approved

Fire Department housing review

Fire Department · SFFD-HQ

Oct 28, 2026Approved-Stipulated

Building plan review

Building Inspection · BLDG

Nov 3, 2026Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 4, 2026Issued Comments

Building plan review

Building Inspection · BLDG

In progress—

Structural plan approval

Building Inspection · PAD-STR

In progress—

Mechanical and energy plan review

Building Inspection · MECH

In progress—

Central Permit Bureau

Building Inspection · CPB

In progress—

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Issued
Estimated cost
$2,100,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Steven David Ehrlich

Ehrlich Yanai Rhee Chaney Arch

ArchitectC10142
Geoffrey Gibson

Winder Gibson Architects

ArchitectC-35924
Jason R Powers

Zfa Structural Engineers

Engineer76130
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202207017587 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record