144 Laidley St
San Francisco permit 202207017622 · Glen Park
Bldg b: erect 4-story over 1 basement, type 5b, single family dwelling with 1 adu. project to include lot split. (demo under pa# 202207017611. new construction bldg a pa# 202207017587).
- Filed
- Jul 1, 2022
- Issued
- Jan 23, 2026 (43 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 50 stops across 6 departments
- Comments issued
- 7 times, by Public Works, Permit Center, Building Inspection
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 1, 2022 | Jul 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 27, 2022 | Aug 9, 2023 | Administrative |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Aug 12, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 15, 2022 | Jun 6, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Aug 15, 2022 | Jun 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 15, 2022 | Sep 2, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 15, 2022 | Jul 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2022 | Jan 3, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 7, 2023 | Mar 16, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 7, 2023 | Mar 9, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 14, 2023 | Mar 14, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 6, 2023 | Jun 6, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 8, 2023 | Jun 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 28, 2023 | Jul 31, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 28, 2023 | Aug 4, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 9, 2023 | Aug 9, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 9, 2023 | Jun 20, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jun 20, 2024 | Jan 23, 2026 | Administrative |
Addendum 1: Excavation/shoring
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 12, 2026 | Feb 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 23, 2026 | Feb 25, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Feb 25, 2026 | Mar 30, 2026 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 25, 2026 | Mar 30, 2026 | Administrative |
Fire prevention review Fire Department · SFFD | Feb 25, 2026 | Mar 2, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Feb 25, 2026 | Mar 17, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 25, 2026 | Apr 3, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Feb 25, 2026 | May 4, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | May 1, 2026 | May 1, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | May 4, 2026 | May 6, 2026 | Administrative |
Addendum 2: Foundation superstructure arch mep t24
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 2, 2026 | Apr 21, 2026 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Apr 21, 2026 | Apr 28, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 29, 2026 | May 19, 2026 | Administrative |
Zoning review Planning · CP-ZOC | May 19, 2026 | May 20, 2026 | Approved |
Building plan review Building Inspection · BLDG | May 19, 2026 | Jul 21, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | May 19, 2026 | Jul 17, 2026 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 19, 2026 | May 22, 2026 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | May 19, 2026 | May 27, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | May 19, 2026 | Jun 26, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 19, 2026 | May 22, 2026 | Approved |
Public Utilities programs review Public Utilities · SFPUC-PRG | May 19, 2026 | May 22, 2026 | Approved |
Permit Processing Center Building Inspection · PPC | May 19, 2026 | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | Jul 17, 2026 | Jul 21, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 13, 2026 | Aug 19, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 29, 2026 | Nov 3, 2026 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Nov 3, 2026 | Nov 3, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2026 | Nov 4, 2026 | Issued Comments |
Building plan review Building Inspection · BLDG | — | In progress | — |
Building plan review quality control Building Inspection · BLDG-QC | — | In progress | — |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $2,100,000
| Name | Role | License on permit |
|---|---|---|
| Steven David Ehrlich Ehrlich Yanai Rhee Chaney Arch | Architect | C10142 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2013